| To use a search path Project uses
specific search paths to locate the values that are required for various
processes. Infor LN uses a search path to default the labor rates. However,
you can modify the priority settings to change the specified search path. By
default, Infor LN considers the search path in this order: - Priority 1
- Priority 2
- Priority 3
- Priority 4
The search path is specified in the Projects (tppdm6100m000) session. Infor LN uses
several search options to locate the labor rate. The search path used to
default the labor rates for the budget lines is: - Project: Project-specific labor rates as specified in the Projects (tppdm6100m000) session, are considered.
- Task: Cost rate as specified in the Tasks (tppdm0511m000) and Project Tasks (tppdm6511m000) sessions, is considered
- Employee: Labor rate specified for the employee as specified in
the Employees - Project (tppdm8101m000) session, is considered.
- Trade group: Labor rates specified for the trade groups in the Trade Group (tppdm0130s000) session, is considered. However, the labor rate is
derived from the Labor Rate Codes (tcppl0190m000)
Infor LN uses this search path to default: The options are: The options for the search path are: - Project: Project-specific labor rate as specified in the Projects (tppdm6100m000) session, is considered.
- Task: Cost rate as specified in the Tasks (tppdm0511m000) and Project Tasks (tppdm6511m000) sessions, is considered.
- Employee: Labor rate specified for the employee in the Employees - Project (tppdm8101m000) session, is considered.
- Trade group: Labor rate specified for the trade groups in the Trade Group (tppdm0130s000) session, is considered.
- Department: The labor rate specified for the department in the Project Management Offices (tppdm0110m000) session, is considered.
Note - If the labor rate is determined using Priority 1, the search
process is stopped.
- If the labor rate is not determined using Priority 1, the
labor rate is determined using the next priorities.
- If you set the Priority 1 field to Labor,
the labor rates specified in the Tasks (tppdm0511m000) and Project Tasks (tppdm6511m000) sessions, is considered.
- If the labor rate is not specified in the Tasks (tppdm0511m000) session, the labor rate specified in the search path
for Priority 2 and so on, is considered.
| |