Overhead Status

  • Open

    The status of the concerning project is Active or Finished and project-phase or status of the element or activity to which overhead must be applied is Released.

  • Not Able to Apply

    It is not possible to apply overhead on a project with status Free, Closed, or Archived or the status of the element or activity set to Free, On Hold, Finished or Closed.

  • Applied

    The overhead is applied to a project.

  • Not Applied

    The overhead is not applied to any project.