Report Orders Completed Globally (tisfc0206m000)

Use this session to report a number of production orders as complete. This can be a range of production orders, or an JSC order group. The quantities reported as complete in the last operation are posted (direct process inbound) to inventory if the quantities are not yet posted.

Note

If the Backflushing Method field is set to Interactive in the Production Order Parameters (tisfc0100s000) session, when clicking Report Complete, you are asked if you want to backflush materials/hours immediately. This question is displayed even if backflushing is not applicable for the selected order(s).

 

Selection Range
Selection

Select how the production orders are chosen.

Allowed values

  • By Order
  • By Group
Site

A business location of an enterprise that can maintain its own logistical data. It includes a collection of warehouses, departments and assembly lines at the same location. Sites are used to model the supply chain in a multisite environment.

These restrictions apply to sites:

  • A site cannot cross countries. The warehouses and departments of the site must be in the same country as the site.
  • A site is linked to one planning cluster. Consequently, all warehouses and work centers of a site must belong to the same planning cluster.
  • A site is linked to one logistic company.

You can link a site to an enterprise unit or an enterprise unit to a site.

If an enterprise unit is linked to a site, the entities of the site belong to the enterprise unit. Conversely, if a site is linked to an enterprise unit, the entities of the enterprise unit belong to the site.

Related topics

Order Selection
Production Order

An order to produce a specified quantity of an item on a specified delivery date.

Project (PCS)

A collection of manufacturing and purchasing actions that are performed for a particular customer order. A project is initiated to plan and coordinate the production of the to be manufactured items.

For a standard-to-order production, the project is only used to link the item with the customer order. A project can also include these:

  • Customized item data (BOMs and routings)
  • Project planning (activity planning)
Scheduling Area

A physical area or part of the production line for which a production schedule is defined. Scheduling areas are defined for repetitive items.

Scheduling areas relate to the production orders of items with routings that employ virtually the same production facilities. A scheduling area is related to a production schedule code.

Scheduling areas are used:

  • To define routing codes by repetitive (RPT) item in the Item - Routings (tirou1101m000) session.
  • As a selection criterion in the Report Orders Completed Globally (tisfc0206m000) session and the Backflush Materials and Hours (tisfc0220m000) session.
Example
Scheduling AreaSchedule Code
HHAHousehold appliancesWLWeekly
ELTElectric tools2WLbiweekly

 

Planned Delivery Date

The date the finished items are finished according to the planning.

Planner

The logon code of the employee who plans plan items.

Group Selection
Production Order Group

Enter the JSC order group whose production orders you want to report as globally complete.

Options
Settings
Completion Date

The date the order is reported as complete.

Default value

The default value is the current date. You can also enter a date in the past.

Related topics

Options
Repetitive Items Only

If this check box is selected, only production orders for repetitive items are reported as complete.

Note

You can make a selection of these production orders with the scheduling area selection fields.

Check on Completion of Last Operation

If this check box is selected, the production order is reported complete only when last operation on the production order has the operation status Completed.

Related topics

Direct Process Inbound

If this check box is selected, inbound orders are processed directly.

Accept Zero Quantities Completed

If this check box is selected, the selected production orders are reported as completed even if the quantity of products to report completed is 0 (that is, the Quantity Delivered field is 0 (zero)).

Print Erroneous Production Orders

If this check box is selected, LN includes error messages in the report that are produced while the production order is processed.

Skip Lot-Controlled Production Orders

If this check box is selected, production orders that are controlled by lot are not reported as complete.

 

Report Complete

Executes the process that you set up in this session.