Job Shop Routing

To support multi-site production, routings are now linked to product per site.

Note

To use this session the Job Shop by Site parameter in the Multisite Concepts Activation (tcemm4600m000) session must be set to Active or In Preparation.

Routing Master Data

To be able to define a routing, these must already be defined:

  1. Define reference operations

    Prerequisite:

  2. Link skills and tools.

    Prerequisite:

  3. Link process variables

    Prerequisite:

New Routing
Note

A routing is always site specific and quantity dependent.

To define a routing for a product:

  1. Use the Job Shop Routing (tirou4600m000) session to generate a new routing revision.

    The revision is assigned the status New on generation.

  2. Specify the site to which the routing will apply in the Site field.
  3. Specify the product for which the routing will be used in the Product field.

    Once the product is selected, the routing ID number and revision will automatically be generated. If a previous routing for this product and site combination exists, the revision number will be upped by one.

    The new routing revision automatically receives the status New.

  4. Edit the routing header as necessary.

  5. Add operations to the routing

    Note: Prerequisite to adding operations that reference operations have been defined int he Reference Operations (tirou4150m000) session.

  6. Once all operations are added use the Validate command to check for consistency.

  7. After validation use the Approve Revision command to change the revision status to Approved.

Standard Routing by Site

A standard routing is a routing that can be coupled to multiple products. Using a standard routing can reduce maintenance.

For more information, refer to Standard Routing