| Production Bill of Material (PBOM) Setup And GenerationThe global bill of
material models the way the item is built, in multiple levels and in multiple
sites, and contains all information that is intrinsic to the item. P-boms are identified by the combination of an item code and the
revision number of the p-bom. The production bill of materials can be maintained manually or
generated using the Engineering Data Management module. To generate a new production bill of material: Generate new revision Specify product Click on the Product field in the Production Bill of Material (timfc3600m000) session to open the Item - Production (tiipd0101m000) session for which you want to define a new
p-bom. Assign revision LN automatically assigns revision number 001 to a new p-bom. Default the effective date Unless otherwise specified the effective date is defaulted
to the current date, with the expiry date set to 9999. Add the production bill of material lines to the materials
tab Add the p-bom lines containing the materials. Note: changes to the material lines can only be made as long
as the p-bom status is New. Validate p-bom Use the Validate Production Bill of Material (timfc3200m000) session to check the new p-bom for
consistency and generate a report. Check production bill of material for
consistency Use the Check Production Bill of Material Consistency (timfc3200m400) session to check for
loops in the p-bom structure, updates of the order system, unit effective
supply and commingling restrictions, as well as project peg indicators and
trade compliance. Approve revision In the Job Shop Bills of Material (tibom3100m000) session, select the p-bom revision and use
the Approve Revision command to change the status from New to Approved.
Note Only applicable if the Job Shop by Site parameter in the Multisite Concepts Activation (tcemm4600m000) session is set to Active or In Preparation. New Production Bill of Material from a E-BOM You can generate a production bill of material from an
E-BOM: - Start the Engineering Item (tiedm0110m000) session.
- Select the E-BOM you want to generate a production bill of
material from.
- Use the Engineering Item Revisions command to start the Engineering Item Revision (tiedm1100m000) session.
- Select the revision you want to copy to a production bill of
material.
- Copy E-BOM header and lines to the production bill of
material.
- The new production bill of material is automatically assigned
the status New, with the current date as the default effective
date.
Changing an existing production bill of
material To make changes to an existing production bill of
material: - Start the Production Bills of Material (timfc3100m000) session.
- Select the production bill of material you want to
edit.
- Use the New Revision command to generate a new
revision.
- Use the Copy Production Bill of Material (timfc3200m100) session to copy the PBOM header data and
material lines to the new revision.
- The revision is automatically assigned the status New, with
the current date as the default effective date.
- Make the necessary changes to the production bill of material
header and BOM lines.
- Use the Validate Production Bill of Material (timfc3200m000) session to check the new p-bom for
consistency and if the materials needed are present before the status is
changed to Approved.
- Once the new production bill of material is approved, LN adjusts the expiry date
of the previous revision in accordance with the effective date of the new
revision.
| |