| Calculation OfficesA calculation office is a work center that determines the enterprise unit for a PCS project or production order. The enterprise unit is
linked to a financial company,
which is financially responsible for a project or production order. Projects
and production orders are always linked to a calculation office, so that LN can book the costs and production results of the production order or project to the financial company. Note Work centers and warehouses can belong to enterprise units that are different from the calculation office's enterprise unit.
The financial transactions of the work centers and warehouses are posted to the
financial companies of their own enterprise units. Alternatively, intercompany trade relationships must be defined between the enterprise
units.
Defining a calculation office of the type
costing Start the Enterprise Units (tcemm0130m000) session Select the enterprise unit for which you want to define
a department. Selecting the enterprise unit, will start the Enterprise Unit (tcemm0630m000) session. In the Enterprise Unit (tcemm0630m000) session, on the Departments tab
you can add a new department. The New Department command displays
a new window. Specify the department type Work Center Specify the work center type Costing Work Center.
In the Work Centers (tirou0101m000) session, you must specify the rest of the calculation
office data.
If the Sites parameter in the Implemented Software Components (tccom0100s000) session is either In Preparation or Active you can also: Start the Sites (tcemm0150m000) session. Select the site for which you want to define a department,
this will start the Site (tcemm0650m000) session. In the Site (tcemm0650m000) session, select the Departments tab. The New Department command displays a
new window. Specify the department type Work Center Specify the work center type Costing Work Center. In the Work Centers (tirou0101m000) session, you must specify the rest of the calculation
office data.
Calculation offices for production orders On a production order's calculation office, LN posts material costs,
operation costs, surcharges, and subcontracting costs. The default calculation office depends on the setting of the Calculation Office defined in field in the Production Order Parameters (tisfc0100s000) session. You can select one of the following options: Note If Standard Cost by Enterprise Unit parameter in the Implemented Software Components (tccom0100s000) session is selected, using the Production Department option as the default for the calculation office is
mandatory. Calculation offices for PCS projects On a PCS project's calculation office, LN posts non-item project
costs, such as project surcharges, hours posted on activities, and general
project costs. Furthermore, the PCS project's calculation office is used to
aggregate the total costs and revenues of the project. Note You can select a regular work center, sales office or
warehouse as the calculation office for a PCS project. Default calculation office for PCS projects If you generate a PCS project on a sales order or service
order, a calculation office for the PCS project can be defaulted in three ways,
dependent on the value in the Enterprise Unit for calc.off. used from field in the Project Control Parameters (tipcs0100m000) session: Department The default calculation office for the PCS project is the
calculation office that is linked to the enterprise unit of the sales office or
the service department. You can define a default calculation office of a
specific enterprise unit in the Enterprise Units (tcemm0130m000) session. Warehouse The default calculation office for the PCS project is the
calculation office that is linked to the enterprise unit of the warehouse. You
can define a default calculation office of a specific enterprise unit in the Enterprise Units (tcemm0130m000) session. None The default calculation office for the PCS project is
determined by the number group and the order series of the sales order, service
order, or production order for which the PCS project is created. You can use
the Default Project Data by Number Group (tipcs0103m000) session to define calculation
offices for combinations of number group and order series.
| |