Production Bill of Material (timfc3600m000)

Use this session to manage materials for the production bill of material.

This session displays data from

Note

To use this session the Job Shop by Site parameter in the Multisite Concepts Activation (tcemm4600m000) session must be set to Active or In Preparation.

 

Product

The product ID.

BOM Quantity

The number of manufactured products to which a bill of materials (BOM) applies. The BOM quantity enables you to specify very small product quantities as BOM components.

Example

You need very small amounts of certain colors to mix one liter of a specific paint, Cotton White. Therefore, a BOM quantity of 1000 liter is defined. The component quantities for the paint can then be as follows:

Paint Cotton White, 1000 liter:
White999 liter
Yellow0.6 liter
Red0.2 liter
Blue0.2 liter

 

Status

The status of the production bill of material.

Allowed values

  • New
  • Approved
  • Expired
Effective Date

The date the P-BOM becomes effective.

Source

The origin of the P-BOM.

Allowed values

Source Type

Source Engineering Item

The item for which the Engineering Bill of Material is defined.

Note

If the P-BOM is created by EDM based on an engineering item- Item Relationship, this field specifies the engineering item.

Source Engineering Revision

The revision of the engineering item bill of material.

Expiry Date

The date the P-BOM can no longer be used.

Created By

The name of the employee responsible for the creation of the PBOM.

Created On

The date the PBOM was created.

Approved By

The employee responsible for the approval of the production bill of material.

Approved On

The date the production bill of material was approved.

Expired By

The eployee responsible for expiring the production bill of material.

Expired On

The date the production bill of material was expired.