|   | Offsetting OptionsInitial If this option is selected, the Initial Start Date must be specified. Note - The Initial Start Date must be in the future.
 - By default, the Initial Start Date is the planned start time of the
			 first position on the last segment of the assembly line. If this date is in the
			 past, it is changed to the current date and time + 5 minutes, or the first
			 available work time in the calendar.
 - This option can only be selected if no assembly has started
			 on the first segment of the assembly line.
 
 Continuous If this option is selected, the new line sequence for each new
		segment is synchronized with the planned end date of the last completed
		position on that segment. Note Continuous is the only option available if assembly has
		  started, but no orders are completed. Backlog If this option is selected, new orders are sequenced from the
		date you specify in the (Re) Plan Start Date field. Note The (Re) Plan Start Date must be in the future. By default, it
		  is the current date and time + 5 minutes, or the first available work time in
		  the calendar. This option is only available if the previous segment was
		  completed. Actual Times If this option is selected, a new line sequence is synchronized
		for each new segment with the the actual completion dates of the
		segment. Note This option is only available if orders have already been
		  completed on the last segment of the assembly line. 
    |   |