Calculate Intermediate Results (ticst0201m100)

Use this session to make intermediate calculations for orders with a long lead time.

 

Selection

Select how the production orders are chosen.

Allowed values

  • By Order
  • By Group
Site

A business location of an enterprise that can maintain its own logistical data. It includes a collection of warehouses, departments and assembly lines at the same location. Sites are used to model the supply chain in a multisite environment.

These restrictions apply to sites:

  • A site cannot cross countries. The warehouses and departments of the site must be in the same country as the site.
  • A site is linked to one planning cluster. Consequently, all warehouses and work centers of a site must belong to the same planning cluster.
  • A site is linked to one logistic company.

You can link a site to an enterprise unit or an enterprise unit to a site.

If an enterprise unit is linked to a site, the entities of the site belong to the enterprise unit. Conversely, if a site is linked to an enterprise unit, the entities of the enterprise unit belong to the site.

Production Order

An order to produce a specified quantity of an item on a specified delivery date.

Order Status

The status assigned to a production order, which indicates the process stage of a production order. For example, Planned, Documents Printed, or Released.

Allowed values

Order Status

Scheduling Area

A physical area or part of the production line for which a production schedule is defined. Scheduling areas are defined for repetitive items.

Scheduling areas relate to the production orders of items with routings that employ virtually the same production facilities. A scheduling area is related to a production schedule code.

Scheduling areas are used:

  • To define routing codes by repetitive (RPT) item in the Item - Routings (tirou1101m000) session.
  • As a selection criterion in the Report Orders Completed Globally (tisfc0206m000) session and the Backflush Materials and Hours (tisfc0220m000) session.
Example
Scheduling AreaSchedule Code
HHAHousehold appliancesWLWeekly
ELTElectric tools2WLbiweekly

 

Project (PCS)

A collection of manufacturing and purchasing actions that are performed for a particular customer order. A project is initiated to plan and coordinate the production of the to be manufactured items.

For a standard-to-order production, the project is only used to link the item with the customer order. A project can also include these:

  • Customized item data (BOMs and routings)
  • Project planning (activity planning)
Item From

The range of items for the calculation.

Grouping Selection
Production Order Group

The production order group that contains the production orders that must be closed. You must first select the check box.

Note

The Production Order Group check box must be selected in the Production Order Groups (tisfc3150s000) session.

Options
Simulate Only

If this check box is selected, LN calculates and prints the calculated production results without booking results to the general ledger.

Method of Order Progress Calculation

The calculation method for the order progress.

Also Determine Additional Calculation Office Variances

If this check box is selected, additional office variances are calculated for the production order.

Write Variances to Inventory

If this check box is selected, the variances over the completed percentage of the production order are written to inventory.

Note

If this option is selected, the inventory value is affected.

Print Financial Transactions

If this check box is selected, the calculated financial transactions are printed by production order.

Print Error Messages Only

If this check box is selected, only error messages are printed in the report.

Repetitive Items Only

If this check box is selected, intermediate results are calculated for repetitive items only.

Settings
Currency for details

The currency used for details of the order line.

Currency for totals

The currency used for totals of the order line.

Sort by Warehouse

If this check box is selected, the production orders are sorted by warehouse in the report.