| Purchase receiptsIn the Purchase Receipts (tdpur4106m000) session: - The received quantity can be less than or more than the ordered
quantity.
- Various purchase receipts can be specified for one purchase
order line. The last receipt is the final receipt.
- The budget check and Receipt Expense update are performed when the receipt is
confirmed. After confirmation, the receipt can still be corrected.
Example Ordered quantity: 100 Received qty | Final
receipt | Budget check | Budget update |
---|
60 | no | no, (60 is less than 100) | - Encumbrance-60
- Receipt Expense+60
| 20 | no | no, (60+20=80 is less than
100) | - Encumbrance-20
- Receipt Expense+20
| 10 | yes | no, (90 is less than
100) | - Encumbrance-20
- Receipt Expense+10
|
Received qty | Final
receipt | Budget check | Budget update |
---|
120 | no | yes, for 120 pcs | - Encumbrance-100
- Receipt Expense+120
| 20 | yes | yes, for 140 pcs | Receipt Expense+20 |
Price and discount change after receipt When a receipt is registered for an order line, in the Change Price and Discounts after Receipt (tdpur4122m000) session, you can still change
price and discounts for the purchase order line. When a price and discount change is saved, a budget check is
executed. If the budget check fails, an error message is given and the change
cannot be saved. Receipt corrections You can change the received quantity for a confirmed receipt,
or make a final receipt non-final in the Correct Purchase Receipt (tdpur4106s100) session. When a receipt correction is saved, a budget check can be
executed. If the budget check fails, a message is displayed and the receipt
correction cannot be saved. These receipt corrections are available: Received quantity is decreased No budget check is required, because the received quantity is
less than the original quantity. For a final receipt, the BAD must be updated
with the new total quantity for the purchase order line. On the budget balance,
the Receipt Expense is decreased with the quantity decrease.
In case of a final receipt, the Encumbrance is not increased. In case of a non-final
receipt, if the total received quantity is less than the ordered quantity, the Encumbrance is increased with the received quantity
decrease. Received quantity is increased The BAD must be updated and a budget check must be executed.
On the budget balance, the Receipt Expense is increased with the quantity increase.
In case of a final receipt, the Encumbrance is not decreased. In case of a non-final
receipt, if the total received quantity is less than the ordered quantity, the Encumbrance is decreased with the received quantity
increase. Final receipt is made non-final No budget check is required, because the total quantity is
still the same after correction. On the budget balance, the Receipt Expense does not change, but the Encumbrance is increased if the total received quantity
is less than the ordered quantity. If the total received quantity is greater
than or equal to the ordered quantity, no update is needed. Non-final receipt is made final No budget check is required, because the total quantity is
still the same after correction. On the budget balance, the Receipt Expense does not change, but the Encumbrance is decreased if the total received quantity
is less than the ordered quantity. If the total received quantity is greater
than or equal to the ordered quantity, no update is needed.
| |