| Check and update the available budgetBudget account distribution (BAD) The available budget for a purchase requisition line, order
line, or receipt line can be checked only if a correct budget account
distribution (BAD) is linked to the line. The generated or defaulted BAD is
used to link the purchase transaction to the budget. A BAD requires this data: Financial company The financial company is determined based on the requisition's
or order's Purchase Office field. If no purchase office is
specified, LN cannot
generate a BAD and check the budget. Ledger account and dimensions The ledger account and dimensions are determined based on the
requisition or order line's General Ledger field. If no general ledger is
specified on the line, a default ledger account and default dimensions are
retrieved from the Mapping Scheme (tfgld4573m000) session. - In a requisition line without a project, the ledger account and
dimensions mapping is defaulted from integration document type, 10001045
Purchase order/General costs.
- In a requisition line with a project, the ledger account and
dimensions mapping is defaulted from integration document type, 10090060 Budget
Procurement/On order.
Budget check date The check date is defaulted from the Budget Control Policy (tfbgc0110m000) session for the relevant document
type. Quantity A total quantity that must be equal to the line's ordered or
received quantity. Therefore, the percentage in the BAD must be equal to
100.
You can view and modify a BAD in the Budget Account Distribution (tcbgc1100m000) session, which you can start by selecting Budget Account Distribution from the appropriate menu
in these sessions: - Purchase Requisition Lines (tdpur2502m000)
- Prepare Conversion Purchase Requisition Lines (tdpur2502m100)
- Purchase Order Lines (tdpur4101m000)
- Purchase Order Line Details (tdpur4101m200)
- Purchase Receipts (tdpur4106m000)
Note If, for example, a purchase requisition line is converted to a
purchase order line, the BAD from the requisition line is defaulted and linked
to the purchase order line. Checking and updating the available budget When the budget is checked for a line, the budget check can
fail. In this case, the Budget Exception check box can be selected in the
applicable session. If this check box is selected, the budget exception must be handled before
you can continue with the purchase procedure. However, the Budget Exception check box is selected only
if: - Insufficient budget is available for the checked
line
- The When Budget is Exceeded field is Block in the Budget Control Policy (tfbgc0110m000) session
To resolve the budget exception, you can, for example, change
the line amount or the BAD. You can then manually check the budget for lines
that have the Budget Exception check box selected and have a
correct BAD. To check the budget, select Check Budget from the appropriate menu in these sessions: - Purchase Requisition Lines (tdpur2502m000)
- Prepare Conversion Purchase Requisition Lines (tdpur2502m100)
- Purchase Order Lines (tdpur4101m000)
- Purchase Order Line Details (tdpur4101m200)
- Purchase Receipts (tdpur4106m000)
Note If insufficient budget is available for a line and the When Budget is Exceeded field is: - Continue, the budget transactions are written and the
purchase procedure can continue.
- Warn, the user is notified about the budget shortage,
but the budget transactions can be written and the purchase procedure can
continue.
| |