| Resource ManagementResource Management functionality can be used to maintain
resource details such as employee, skill level, estimated time, start date, and
end date. This data can be used to plan and allocate resources,
effectively. - In the Characteristic Tests (qmptc0105m000) session, for a specified testing combination,
specify the Test Time Per, Test Skill, and the Employee. This data is defaulted in the order
inspection and can be used to understand the time required by an employee to
test an inspection order line.
- In the Inspection Order Lines (qmptc1101m000) session, for an employee, specify the Planned Start Date and the Planned Completion Date for an inspection order line
linked to an order inspection.
- In the Order Inspections (qmptc1120m000) session, for an order inspection, the Planned Start
Date and Planned End Date is displayed. The Planned Start Date is the earliest
date specified amongst all of the inspection order lines. The Planned End Date
is the last date specified amongst all the inspection orders.
- In the Resource Assignments (tcrac1100m000), you can view the employee, order
inspection, planned start date and end date.
Note This functionality is applicable only to NCMR and
CAP. | |