Material for multiple operationsIf the same material is used in several sequential operations, it is recommended to issue the material at the start of the production order. Therefore, in the Bill of Material (tibom1110m000) session, enter 0 (zero) in the BOM line's Operation field. To improve performance, do not define a material-routing relationship in the BOM Line - Material-Routing Relationships (tibom0140m000) session. To issue the material required for a phantom at the start of the production order, in the Item - Production (tiipd0101m000) session, set the Turn Operation 0 into First of field to First Operation of Production Order. Performance aspects
| |||