|   | VMI business partner selectionThis topic describes how LN selects a supplier
		in a vendor managed inventory (VMI) situation. Some restrictions for the use of VMI functionality are also
		described. Only a single VMI supplier can carry out your planning for an item at
		any single time. However, you can switch from one VMI supplier to another. LN searches for
		suppliers with terms and conditions agreements effective between the current
		date ('now') and the scenario finish date. To select the effective VMI suppliers, the following rules
		  apply: - If LN finds multiple valid VMI suppliers, LN sorts the suppliers according to the effective dates and expiry dates of their respective terms and conditions agreements.
 - If the effectivity period of one VMI supplier
		  completely encloses the effectivity period of another VMI supplier, that other
		  VMI supplier is ignored.
 - As soon as a valid supplier becomes effective, LN selects that
		  supplier as the VMI supplier.
 If, at a particular date, no supplier is effective as VMI
			 supplier, no more VMI suppliers can be selected for later dates. For example,
			 you cannot have a supplier carry out the planning in March, then use regular
			 planning methods in April, and have the supplier carry out the planning again
			 in May. If you try this, Enterprise Planning generates a signal and handles the second period (May in the example)
			 by using the regular supply method. However, of the total period between the current date and
			 the scenario finish date, you can use regular planning in the first part of the
			 period, later, a VMI supplier can carry out the supply planning for a
			 particular time, and in the last part of the period you can use regular
			 planning again. 
 Multiple sourcing Multiple sourcing is permitted, as long as no more than one of
		  the suppliers is a VMI supplier. If you use multiple sourcing, the order planning procedure
		  generates requirements and distributes the requirements over the available
		  sources in the usual way. The demand that is allocated to the VMI supplier
		  results in forecast that is sent to the VMI supplier. The other
		  demand results in planned purchase orders or planned distribution orders. You can assign a priority to the various suppliers, but the
		  VMI supplier always has priority 0, which is the highest priority. To view all active VMI suppliers and regular suppliers for a
			 plan item, take the following steps: - Start the Items - Planning (cprpd1100m000) session.
 - Select the plan item.
 - Click appropriate menu > Product Structure > Active Suppliers by Plan Item.
 
    |   |