|   | RRP run, item selectionThis section describes how LN selects the items to
		plan in the Generate Order Planning (cprrp1210m000) session and the Generate Order Planning (Item) (cprrp1220m000) session. Net-change planning For each plan item, LN records if a change
			 has occurred since the last simulation, for example, a change in the bill of
			 material or changed demand figures. LN also records the earliest date on which a
			 change has occurred ( net change date). You can have the order-planning sessions to plan only the
			 items for which planning data changed since the last planning run. Bottom-up item selection To investigate the effects of a change in availability of
			 some critical component that is used in many end products, you can use the
			 bottom-up item-selection feature. In a bottom-up planning run, the LN plans every item that
			 somehow relies on the availability of the originally selected plan item. Top-down item selection To perform a complete planning run for some high-priority
			 sales order, for example, for a sophisticated customized (engineer-to-order)
			 end item, you can use the top-down item-selection feature. In a top-down planning run, LN plans every purchased
			 item and subassembly of which the timely availability can influence the
			 production of the originally selected plan item. Restrictions LN applies the following restrictions to the selection of plan items, for which LN generates the order
				planning: - LN only includes plan items that you defined on the specified plan level.
 - Bottom-up item selection does not work for items with a standard-to-order (STO) structure.
 - Both top-down and bottom-up select the related items on one company. The selection algorithm stops as soon as it
				encounters a company change.
 
 Selection procedure LN determines the set of plan items to plan in the following way: Selection range LN selects the plan item you specified in the Generate Order Planning (Item) (cprrp1220m000) session or the range of plan items you
				specified in the Generate Order Planning (cprrp1210m000) session. Bottom-up selection If you select the Include Parent Items check box, for the selected plan items, LN also includes the
					 following items: - Parent items on the bill of material (BOM).
 - Receiving items specified in the Supplying Relationships (cprpd7130m000) session.
 - Parent items on the generic bill of material (BOM) for the generic items
					 included in the item range.
 - Derived items: The project items for which you created
					 a project in the Project Control module in Manufacturing.
 Alternatives 
 The bottom-up selection works in a multilevel way. For
				  example, LN also selects
				  the parent item of the parent item, up to the end items that can be sold to
				  customers. Top-down selection If you select the Include Child Items check box, for the selected plan items, LN also includes the
					 following items: - Components on the bill of material.
 - Supplying items that you specified in the Supplying Relationships (cprpd7130m000) session.
 - Components on the generic bill of material (BOM), for
					 the generic items included in the item range.
 Derived-from items: The generic or normal items that
						you use to create project items in the Project Control (PCS) module of
						Manufacturing, and from which the project items included in the specified item
						range are derived. If, during the order-based planning, the project
						structure of a project item must be built up, this also works together with the
						top-down item selection algorithm. For example, if during order-based planning, LN finds out that supply
						must be generated for project item PX, LN copies the structure
						of item X. In that case, LN must also create new project items. These
						newly created project items are also taken into account during the planning. Alternatives 
 The top-down selection works in a multilevel way. For
				  example, LN also selects
				  the components of the components, up to the purchased parts. Restrictions LN applies the restrictions listed previously under "Restrictions" to the plan
				item selection. - If you selected the Run a Net Change Planning check box, LN restricts the planning
				run to plan items of which the planning parameters, or item structure has
				changed since the previous order-planning run. For details, refer to Net-change simulations.
 Phantom items If the  Inherit Warehouse if Parent Item is a Phantom check
				box in the Bill of Material (tibom1110m000) session is selected for any of the selected
				plan items, Enterprise Planning selects plan items for  all clusters for
				the material. For more information, refer to  Direct material supply (DMS)
 
 For examples of this procedure, refer to Item selection in order planning, examples.    |   |