|   | Simulated time period (RRP run)An order simulation (RRP run) is always carried out for a
		  particular time period. The simulated time period is limited by a number of
		  factors: - The start date and end
		  date of the scenario, defined in the Scenarios (cprpd4100m000) session.
 - The time fence and the order horizon of the item,
		  defined in the Items - Planning (cprpd1100m000) session.
 
 Firm-planned orders A firm-planned order serves as
			 a sort of additional time fence: LN does not generate planned orders before the
			 last firm-planned order. If necessary, LN generates
			 reschedule-in messages. However, you can override this rule by selecting the Planned Order before Firm/Actual check box in the Planning Parameters (cprpd0100m000) session. Simulate in time fence If you select the Generate within check box, the time fence is ignored and the simulation can
			 start at the current date. Net-change simulation 
    |   |