| Determination of calendar correctionWhen LN determines the planned delivery date and the planned receipt date
in the Warehousing Orders (whinh2100m000) session, LN takes into account
the calendars of the ship-from data and the ship-to data to determine the
required calendar correction. LN determines the calendar correction for ship-from data and ship-to
data in the same way. The calendar correction determination only differs in the
following way: - If the calendar correction must be determined for the ship-from
data, LN uses the Ship-from Code.
- If the calendar correction must be determined for the ship-to
data, LN uses the Ship-to Code.
To be able to add a calendar correction, LN searches for a
calendar as follows: - If the Ship-from Code or the Ship-to Code is a warehouse, LN searches for a
calendar in the following sequence: the address' calendar, then the warehouse's
calendar, and then the company's calendar. In all other cases, LN uses the address'
calendar. If LN cannot
find any calendar, a calendar correction does not take place.
-
If a calendar is found, LN searches for the
actual calendar based on: - LN determines the calendar correction based on the actual calendar's start time
and end time.
Note - You can view the actual calendar in the Calendar Working Hours (tcccp0120m000) session.
- You can define the availability type in the Warehouse Master Data Parameters (whwmd0100s000) session.
| |