Project pegging for Service Order and ActivitiesYou must select the Use Project Pegging in Field Service check box in the Service Order Parameters (tssoc0100m000) session to implement project pegging for service orders. If this check box is cleared, the existing project-service integration functionality is implemented. You can specify the project peg:
If a service order is project pegged, the service order costs are linked to the project when the costs are logged on the service order WIP. If the serialized item specified for a service order is linked to a service contract configuration line, Infor LN defaults the project pegging data in the Service Orders (tssoc2100m000) and the Service Order Activities (tssoc2110m000) sessions from the Service Contracts (tsctm3100m000) session. If the Costing Breaks check box is selected in the Implemented Software Components (tccom0100s000) session, the Project Peg Origin field in the Service Orders (tssoc2100m000) session is set to:
Project pegging for service orders When you create a service order, if the Use Project Pegging in Field Service check box is selected in the Service Order Parameters (tssoc0100m000) session, the project pegging data in the Service Orders (tssoc2100m000) session is defaulted from the originating object. However, you can modify this value for service orders with the Status, Free. If the Manual Project Peg Modification check box is selected in the Project Pegging Parameters (tcpeg0100m000) session, you must specify a reason code when you modify the project pegging data on the service order header. Note
Project pegging for service order activities When you create a service order activity, the project pegging data in the Service Order Activities (tssoc2110m000) session is defaulted from:
You cannot modify the project pegging data for a service order activity. Project pegging for service order cost lines When you create service order cost lines (material, labor or other), the project pegging data is defaulted from the Service Order Activities (tssoc2110m000) session, the Service Orders (tssoc2100m000) session or from:
Project pegging for a service order while creating a
copy When you create a copy of an existing service order, the project pegging data is also copied if the Project Pegs check box is selected in the Copy Service Order (tssoc2280m000) session. If the project pegging data of the existing order is modified manually, and this data must be copied to the new service order, you must specify the Change Reason in the Copy Service Order (tssoc2280m000) session. Project pegging for service order material cost line while
planning and releasing If the Project Pegged Inventory check box is selected in the Service Order Estimated Material Costs (tssoc2120m000) session:
Project pegging when subcontracting a service order
activity If a service order activity is subcontracted, a service order other cost line of Cost Type Subcontracting is created, when the service order is planned. The project pegging data is defaulted from the Costing Breaks - Service Material (tppdm3103m000) session if the Costing Breaks check box is selected in the Implemented Software Components (tccom0100s000) session. Else, the project pegging data is defaulted from the linked service order activity. Project pegging when registering service order actual
costs When the actual costs are registered, project pegging data is linked to the existing financial transactions, to log costs to the appropriate PCL. The integration elements of each financial transaction are extended with the project pegging data. When the actual costs are registered for the service order material costs and the service order other costs, these costs are logged on the PCL. If the item is specified on the service order material cost line or service order other costs line, this item is used to identify the project cost type. Else, the cost component is used to identify the project cost type. The cost component is identified using the Cost Mappings (tcmcs0149m000) session. However, when hours are logged in LN Service, LN People log the cost on the PCL and to book the project peg on the Labor lines of the service order, a project peg is transferred from LN People. Project pegging when costing service order actual
costs When costing the service order actual cost lines, the invoice is created in LN Central Invoicing. If the service order is linked by the project peg to a project in LN Project (or by the old Service Order links by Project (tppss65m000)), costs are rolled up to the project:
Note If costs are covered by a contract, (repair) warranty, field change order costs or goodwill, these costs are not rolled up to the project. Project pegging when closing service orders When closing a service order, the service order data can be copied to history. The project pegging data of the service order, activities and the cost lines is also copied to history. When project pegging data is specified in Field Service, the project can be closed if all related service orders are closed. When project pegging data is not specified in Field Service, the project can be closed if all the service orders linked to the Project have the status Final (that is, if all costs are rolled up to the project).
| |||