| To create an item breakdown from a standard production BOMYou can use the Create Item Breakdown from Standard Production BOM (tscfg1210m200) session to copy
a production BOM to an item breakdown. This
functionality can help you create Installation groups. Note - You must implement Manufacturing to use this
session. Select the Manufacturing (TI) check box in the Implemented Software Components (tccom0500m000) session.
- The item breakdown can
contain less items than the production BOM.
Step 1. Start the Item Breakdowns (tscfg1110m000) session. Step 2. On the appropriate menu, click Create from Standard
Production BOM to start the Create Item Breakdown from Standard Production BOM (tscfg1210m200) session. Step 3. Enter or select the top item to copy from in the Production
BOM field. Step 4. Under Settings, select the Check Effectivity check box to
enter a date that LN uses to check the validity of the production-BOM item. LN only copies the
items that are valid on the entered date. To copy all the items, clear the
Check Effectivity check box . Note - If the item breakdown already exists for the top item in the
production BOM, the question "Item Breakdown Already Exists. Overwrite?"
appears. If you click Yes, the existing item breakdown is completely replaced.
- Make sure that the default item data is present in the Item Defaults (tcibd0102m000) session for the combination of item type and item
group of the production-BOM items.
- The BOMs of customized items cannot be
copied. You can copy the customized BOM to a standard production BOM with the Copy Customized Product Structure to Standard Structure (tipcs2232m000) session and
proceed as described in this topic.
- LN always creates the item breakdown for one (1) parent item. Therefore, if the
BOM quantity of the top item in the production BOM is greater than one (1), LN converts the
quantity of the BOM items to a top-item quantity of one (1).
- If you create an item breakdown for manufactured
items with a BOM quantity greater than one (1), this can result in a decimal
quantity of the item-breakdown components.
- LN copies production-BOM (P-BOM) items listed in the Items - Service (tsmdm2100m000) session or the Items - Service Defaults (tsmdm2105m000) session to the new item breakdown. Note P-BOM Items that are
only listed in the Items - Service Defaults (tsmdm2105m000) session are copied (based on the defaults) to the Items - Service (tsmdm2100m000) session, by LN, when you create the new item breakdown.
- LN copies the production-BOM items with a quantity greater than zero (0).
- LN copies the production-BOM items that are serial-number controlled. Make sure
that the Serialized check box in the Items (tcibd0501m000) session is selected for the BOM items.
- You can create a physical breakdown from the
item breakdown with the Create Physical Breakdown Structure (tscfg2210m000) session.
| |