To transfer planned activities to service ordersUse this process to create planned activities and transfer the planned activities to service order. Step 1. Define Preventive Maintenance Scenario and Preventive Maintenance Line Use the Preventive Maintenance Scenarios (tsspc1130m000) session to maintain preventive maintenance scenarios based on which a maintenance plan, consisting of planned activities, is generated. Use the Preventive Maintenance Scenario (tsspc1630m000) session to create or maintain preventive maintenance scenario lines. You can list the reference activities that constitute an item's maintenance scenario in the Preventive Maintenance Scenario (tsspc1630m000) session. Scenarios can be:
Step 2. Generate Activity Pattern Use the Generate Activity Pattern (tsspc1232m000) session to generate an activity pattern for a range of items based on the reference activities linked for the items. Step 3. Rule Book for Maintenance Scenario Use the Rule Book for Maintenance Scenarios (tsspc1135m000) session to create and maintain preventive maintenance scenario assignment rules. When generating maintenance plans these maintenance scenario assignment rules determine the valid maintenance scenario based on which planned activities are generated. Use this session to link the Service Item Group, Serialized Item Group and Installation Group to the Generate Activity Pattern (tsspc1232m000) session. Step 4. Generate Planning Use the Generate Maintenance Plan (tsspc2200m000) session to generate maintenance planning for a range of installation group. Step 5. Transfer Planning to Service Order Use the Transfer Planned Activities to Field Service (tsspc2220m000) session, to transfer planned activities to a service order. The planned activities must meet the following conditions:
Note
| |||