The project code.
Activity Physical Progress (tpppc1560m000)Use this session to list the progress of activities for a project. Note If you have started this session by zooming, you can only find and select a record.
Project The project code. Description The description or name of the code. Status The project status. Date The date for which forecast will be generated. Activity The activity's code. Description The description or name of the code. Status The work authorization status of the activity. Phys. progress quantity The budgeted number of activities. The progress is compared with this quantity. Unit The unit defined for the activity in the Activities (tppss2100m000) session. Cumulative [Quantity] The number of activities to be invoiced. Cumulative [%] The total progress for this activity, as a percentage. Reported Completed If this check box is selected, the production of the selected activity is completed. You can still enter the progress. Approved Indicates that the physical progress of the activity is approved. Note
Text If this check box is selected, a text is present.
Approve Approves the selected physical progress of the activity. Unapprove Disapproves the selected approved physical progress of the activity.
| |||