The project code.
You can only select projects in which:
- The project status is Active.
- The Control by field in the Projects (tppdm6100m000) session is Elements Budget.
Element Physical Progress (tpppc1550m000)Use this session to list the element progress for a project. This session can only be used if you entered a Progress Quantity in the Elements (tpptc1100m000) session for your element.
Project The project code. You can only select projects in which:
Project Status The project status. Date The progress date. LN checks whether you can still enter progress on this project. Element The element code. Physical Progress Quantity The budgeted number of elements. Cumulative [Quantity] The number of elements to be invoiced. Cumulative [%] The element progress in percentages. Reported Completed If this check box is selected, the production of the selected element is assumed to be completed. If it is not completed, you can still enter a progress. If the progress does not equal 100%, you can settle the difference if:
Approved Indicates that the physical progress of the element is approved. Note
Text If this check box is selected, a text is present.
Approve Approves the selected physical progress of the element. Unapprove Disapproves the selected approved physical progress of the element.
| |||