Element Physical Progress (tpppc1550m000)

Use this session to list the element progress for a project. This session can only be used if you entered a Progress Quantity in the Elements (tpptc1100m000) session for your element.

 

Project

The project code.

You can only select projects in which:

  • The project status is Active.
  • The Control by field in the Projects (tppdm6100m000) session is Elements Budget.
Project Status

The project status.

Date

The progress date. LN checks whether you can still enter progress on this project.

Element

The element code.

Physical Progress Quantity

The budgeted number of elements.

Cumulative [Quantity]

The number of elements to be invoiced.

Cumulative [%]

The element progress in percentages.

Reported Completed

If this check box is selected, the production of the selected element is assumed to be completed. If it is not completed, you can still enter a progress.

If the progress does not equal 100%, you can settle the difference if:

  • The To be Settled check box in the Elements (tpptc1100m000) session is selected.
  • The selected cost object belongs to an extension for which the Extension Type field in the Extension (tpptc0110s000) session is Quantities to be Settled.
Approved

Indicates that the physical progress of the element is approved.

Note
  • Element progress that is approved cannot be modified or deleted.
  • Progress invoice installments can be generated only for approved element progress using the Create Progress Invoice Installments (tppin1210m000) session.
  • Approved element progress which is invoiced cannot be disapproved (Unapprove).
Text

If this check box is selected, a text is present.

 

Approve

Approves the selected physical progress of the element.

Unapprove

Disapproves the selected approved physical progress of the element.