| Time Phased Hours by ProjectThe Time Phased performance report allows you to review the time
phased budget data and the actual hours utilized for the current and the
cumulative period. Time phasing is based on the Earned Value (EV) method,
defined for the activity. The following reports can be generated: - Time Phased Hours by Project
- Time Phased Hours by Project/ Activity
- Time Phased Hours by Project/ Activity/ Cost
Component
- Time Phased Hours by Project/ Activity/ Control Code
To generate the report: - Specify the range of data for which the report must be
generated.
- Review the data.
- Click the project code in the Project field.
- Click Time Phased Hours by Project/ Activity to view the report
for time phased hours for the current and cumulative period, at the activity
level.
![[...]](../../images/time_phased_hours_project.png) - Review the time phased hours data for the current and
cumulative period at the activity level for the project.
- Click the activity code in the Activity field.
- Click Time Phased Hours by Project/ Activity/ Cost Component or
the Time Phased Hours by Project/ Activity/ Control Code to view the report for
the time phased hours for the current and the cumulative period, at the cost
component or the control code level.
![[...]](../../images/time_phased_hours_proj_act.png) - Review the time phased hours data at the cost component or
control code level for the activity, for the current and cumulative
period.
Note At the cost component level and the control code level, the
time phased hours report is displayed only for the cost type, Labor. | |