Time Phased Hours by Project

The Time Phased performance report allows you to review the time phased budget data and the actual hours utilized for the current and the cumulative period. Time phasing is based on the Earned Value (EV) method, defined for the activity.

The following reports can be generated:
  • Time Phased Hours by Project
  • Time Phased Hours by Project/ Activity
  • Time Phased Hours by Project/ Activity/ Cost Component
  • Time Phased Hours by Project/ Activity/ Control Code
To generate the report:
  1. Specify the range of data for which the report must be generated.
  2. Review the data.
  3. Click the project code in the Project field.
  4. Click Time Phased Hours by Project/ Activity to view the report for time phased hours for the current and cumulative period, at the activity level. [...]
  5. Review the time phased hours data for the current and cumulative period at the activity level for the project.
  6. Click the activity code in the Activity field.
  7. Click Time Phased Hours by Project/ Activity/ Cost Component or the Time Phased Hours by Project/ Activity/ Control Code to view the report for the time phased hours for the current and the cumulative period, at the cost component or the control code level. [...]
  8. Review the time phased hours data at the cost component or control code level for the activity, for the current and cumulative period.
Note

At the cost component level and the control code level, the time phased hours report is displayed only for the cost type, Labor.