Hours Forecast by Project
The Hours Forecast by Project report allows the project manager
to analyze the planned hours, the actual hours utilized to complete the project
and determine the variance, for the specified range of data.
Select the required project to view the hours forecast data of
the project at the activity level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
An area of commercial endeavor. Projects can be categorized
based on the business sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the project.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
The report displays:
Project
The project for which the forecast report is
generated.
Planned Hours
The budgeted number of hours required for the completion of the
project.
Actual Hours
The actual number of hours utilized to complete the
project.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Hours
Estimate At Completion (EAC)
Variance At Completion (VAC)
Variance At Completion is the difference between the
budgeted hours and the estimated hours, at the completion of the
project.
Variance At Completion = Planned Hours - Estimate At Completion