Cost Forecast by Project/ Activity/ Control Code
The Cost Forecast by Project/ Activity/ Control Code report
allows the project manager to analyze the expected future costs, the total cost
required to complete the project and determine the budget variance, at the
control code level.
To generate the report, specify:
Company
The code of the company.
Project
The project (range) for which budget report is
generated.
Activity (Description)
The activity linked to the project.
Currency Type
The type of the currency used to display the data in the
report.
The report displays this data:
Control Code (Description)
The control code linked to the project.
Currency
The currency used to display the data in the report. Note: This value is based
on the selected Currency Type.
Budget
The budget data is based on the last approved version in the
BI.
Actual Cost
The cost data is populated from Infor LN.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Cost
Estimate At Completion (EAC)
Variance At Completion (VAC)
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion