Cost Forecast by Project/ Activity
The Cost Forecast by Project/ Activity report allows the project
manager to analyze the expected future costs, the total cost required to
complete the project and determine the budget variance, at the activity
level.
Select the required activity to view the forecast data of the
project at the project/ activity/ control code level.
To generate the report, specify:
The report displays this data:
Activity (Description)
The activity linked to the project.
Progress %
Currency
The currency used to display the data in the report. Note: This value is based
on the selected Currency Type.
Budget
The budget data is based on the last approved version in the
BI.
Actual Cost
The cost data is populated from Infor LN
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Cost
Estimate At Completion (EAC)
Variance At Completion (VAC)
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion