Viewing data in Reports

To view data in reports:

  1. Create Project and structure.
  2. Link OBS to the project, if required.
  3. Create Contract and Contract Line.
  4. Link the Project to Contract Line.
  5. Create Baseline.
  6. Create Budget.
  7. Activate Project, Contract and Contract Line.
  8. Approve the baseline.
  9. Generate the control data.
  10. Publish the budgets using the Project BODs staging session.
  11. Maintain the earned value data in Infor LN.
  12. Budget or Planned value can now be viewed in the reports.
  13. Earned value will be calculated based on the earned value data and can be viewed in the reports.
  14. Maintain costs and progress percentage in Infor LN for the projects displayed in the reports.
  15. Maintain the Revenues.
  16. Generate the Interim Results.
  17. Check the data in BI after the cube jobs are executed.
Note

Data (published or maintained) will be refreshed only after these jobs are executed.