The Budget vs Actual by Project/ Activity report displays the
actual cost against the available budget for the project, at the activity
level.
Select the required activity and click Budget vs Actual by
Project / Activity / Cost Component or Budget vs Actual by Project / Activity /
Control Code to view the report for:
The budget vs actual data at the project/ activity/ cost
component level
The budget vs actual data at the project/ activity/ control
code level
To generate the report, specify:
Company
The code of the company.
Currency Type
The type of the currency used for the project.
Project
The code of the project for which the report is
generated.
Budget vs Actual by Project/ Activity/ Cost Component
Budget vs Actual by Project/ Activity/ Cost Component
The Budget vs Actual by Project/ Activity/ Cost Component
report displays the actual cost against the available budget for the project,
at the cost component level.
To generate the report, specify:
Company
The code of the company.
Currency Type
The type of the currency used for the project.
Project
The code of the project for which the report is
generated.
Budget vs Actual by Project/ Activity/ Control Code
Budget vs Actual by Project/ Activity/ Control Code
The Budget vs Actual by Project/ Activity/ Control Code report
displays the actual cost against the available budget for the project, at the
control code level.
To generate the report, specify:
Company
The code of the company.
Currency Type
The type of the currency used for the project.
Project
The code of the project for which the report is
generated.
The Budget vs Actual Hours by Project report displays the
planned hours against the actual hours of the project, for the available
budget.
Select the required project and click Budget vs Actual Hours by
Project/ Activity to view the report.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project (range) for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
An area of commercial endeavour. Projects can be categorized
based on the business sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the project.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
The report displays:
Project
The code of the project for which the report is
generated.
Planned Hours
The budgeted hours required for the completion of the
project.
Actual Hours
The actual hours utilized for the completion of the
project.
Balance Hours
The balance hours calculated using the formula:
(Planned Hours - Actual Hours)
Budget %
The balance amount expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100
Budget vs Actual Hours by Project/ Activity
Budget vs Actual Hours by Project/ Activity
The Budget vs Actual Hours by Project/ Activity report displays
the planned hours against the actual hours of the project for the available
budget at the activity level.
Select the required activity and click Budget vs Actual Hours
by Project / Activity / Cost Component or Budget vs Actual Hours by Project /
Activity / Control Code level to view the report for:
The budget vs actual hours data at project/ activity / cost
component level
The budget vs actual hours data at project/ activity / control
code level
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which budget report must be
generated.
The report displays:
Activity
The activity linked to the project.
Status
The status of the budget.
Planned Hours
The budgeted hours required for the completion of the
project.
Actual Hours
The actual hours utilized for the completion of the
project.
Balance Hours
The balance hours calculated using the formula:
(Planned Hours - Actual Hours)
Budget %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100
Budget vs Actual Hours by Project/ Activity/ Cost Component
Budget vs Actual Hours by Project/ Activity/ Cost Component
The Budget vs Actual Hours by Project/ Activity/ Cost Component
report displays the planned hours against the actual hours of the project for
the available budget, at the cost component level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the budget report is
generated
The budgeted hours required for the completion of the
project.
Actual Hours
The actual hours utilized for the completion of the
project.
Balance Hours
The balance hours calculated using the formula:
(Planned Hours - Actual Hours)
Budget %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100
Budget vs Actual Hours by Project/ Activity/ Control Code
Budget vs Actual Hours by Project/ Activity/ Control Code
The Budget vs Actual Hours by Project/ Activity/ Control Code
report displays the planned hours against the actual hours of the project for
the available budget, at the control code level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated
The budgeted hours required for the completion of the
project.
Actual Hours
The actual hours utilized for the completion of the
project.
Balance Hours
The balance hours calculated using the formula:
(Planned Hours - Actual Hours)
Budget %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100
Note
In the graphical representation of the budget, the percentage
of balance budget amount is indicated using various colours:
Blue - : Percentage of
the budget used for the project.
Yellow - : Percentage
of the budget available for the project.
Red - : Percentage of
the available budget for the project is negative.
Time Phased Performance
Time Phased Performance
Time Phased Project Performance
Time Phased Project Performance
The Time Phased Project performance report allows you to review
the time phased budget and the actual cost data of the project for the current
and the cumulative periods. Time phasing is based on the Earned Value (EV)
method specified for the activity.
Select the required project and click Time Phased Budget vs
Actuals by Project/ Activity to view the report.
To generate the report, specify:
Currency Type
The type of the currency used for the project.
Company
The code of the company.
Project
The code of the project (range) for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
An area of commercial endeavour. Projects can be categorized
based on the business sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the project.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
Actual Cost
Actual Cost = Actual Cost + Hard Commitment
or
Actual Cost = Actual Cost + Hard Commitment + Soft
Commitment
The report displays this data:
Project
The code of the project for which the report is
generated.
Currency
The project currency. Note: This
value is based on the Currency Type, selected in the settings.
Period/ Cumulative
Year
The current/ cumulative year for which report is
generated.
Period
The current/ cumulative period of the year for which report
is generated.
Budget
The budget allocated to the project in the current/
cumulative period.
Actual Cost
The actual cost incurred on the project in the current/
cumulative period.
Balance Budget
The balance amount in the current/ cumulative period,
calculated using the formula:
(Budget - Actual Cost)
Balance Budget %
The balance amount expressed as a
percentage:
((Budget - Actual Cost)/ Budget))*100
Time Phased Budget vs Actuals by Project/ Activity
Time Phased Budget vs Actuals by Project/ Activity
The Time Phased Budget vs Actuals by Project/ Activity report
displays the time phased budget and actual cost data of the project for the
current and the cumulative periods, at the activity level. Time phasing is
based on the Earned Value (EV) method specified for the activity.
Select the required activity and click Time Phased Budget vs
Actuals by Project/ Activity/ Cost Component report or Time Phased Budget vs
Actuals by Project/ Activity/ Control Code to view the report for:
The time phased budget vs actual cost data at the project/
activity/ cost component level
The time phased budget vs actual cost data at the project/
activity/ control code level
To generate the report, specify:
Company
The code of the company.
Currency Type
The type of the currency based on which the report is
generated.
Project
The code of the project for which budget report is
generated
Period (Monthly)
The periods of the year (range) for which report is
generated.
The report displays this data:
Activity (Description)
The activity linked to the project.
Currency
The project currency. Note: This
value is based on the Currency Type, selected in the settings.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Budget
The budget allocated to the project in the current/
cumulative period.
Actual Cost
The actual cost incurred on the project in the current/
cumulative period.
Balance Budget
The balance amount in the current/ cumulative period,
calculated using the formula:
(Budget - Actual Cost)
Balance Budget %
The balance amount expressed as a
percentage:
((Budget - Actual Cost)/ Budget))*100
Time Phased Budget vs Actuals by Project/ Activity/ Cost
Component
Time Phased Budget vs Actuals by Project/ Activity/ Cost
Component
The Time Phased Budget vs Actuals by Project/ Activity/ Cost
Component report displays the time phased budget data and actual cost data of
the project for the current and the cumulative periods, at the cost component
level. Time phasing is based on the Earned Value (EV) method defined for the
activity.
To generate the report, specify:
Company
The code of the company.
Currency Type
The type of the currency used by the project.
Project
The code of the project for which the report is
generated
Activity
The code of the activity linked to the project.
Period (Monthly)
The periods of the year (range) for which report is
generated.
The project currency. Note: This
value is based on the Currency Type, selected in the settings.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Budget
The budget allocated to the project in the current/
cumulative period.
Actual Cost
The actual cost incurred on the project in the current/
cumulative period.
Balance Budget
The balance amount in the current/ cumulative period,
calculated using the formula:
(Budget - Actual Cost)
Balance Budget %
The balance amount expressed as a
percentage:
((Budget - Actual Cost)/ Budget))*100
Time Phased Budget vs Actuals by Project/ Activity/ Control
Code
Time Phased Budget vs Actuals by Project/ Activity/ Control
Code
The Time Phased Budget vs Actuals by Project/ Activity/ Control
Code report displays the time phased budget data and actual cost data of the
project for the current and the cumulative periods, at the control code level.
Time phasing is based on the Earned Value (EV) method specified for the
activity.
To generate the report, specify:
Company
The code of the company.
Currency Type
The type of the currency based on which the report is
generated.
Project
The code of the project for which budget report is
generated
Activity
The code of the activity linked to the project.
Period (Monthly)
The periods of the year (range) for which report is
generated.
The project currency. Note: This
value is based on the Currency Type, selected in the settings.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Budget
The budget allocated to the project in the current/
cumulative period.
Actual Cost
The actual cost incurred on the project in the current/ cumulative
period.
Balance Budget
The balance amount in the current/ cumulative period,
calculated using the formula:
(Budget - Actual Cost)
Balance Budget %
The balance amount expressed as a
percentage:
((Budget - Actual Cost)/ Budget))*100
Time Phased Hours by Project
Time Phased Hours by Project
The Time Phased performance report allows you to review the time
phased budget data and the actual hours utilized for the project in the current
and the cumulative periods. Time phasing is based on the Earned Value (EV)
method, specified for the activity.
Select the required project and click Time Phased Hours by
Project/ Activity to view the report.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project (range) for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
The section of economy related to business and corporate
organizations. Projects can be categorized based on the business
sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the project.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
The report displays:
Project
The code of the project for which the report is
generated.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Planned Hours
The estimated number of hours required for the completion
of the project in the current/ cumulative period. Calculations are based on the
Earned Value (EV) method, defined on the activity.
Actual Hours
The actual hours used to complete the project in the
current/ cumulative period.
Balance Hours
The balance hours in the current/ cumulative period,
calculated using the formula:
(Planned Hours - Actual Hours)
Balance Hours %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100
Time Phased Hours by Project/ Activity
Time Phased Hours by Project/ Activity
The Time Phased Hours by Project/ Activity report displays the
time phased budget data and the actual hours utilized for the project in the
current and the cumulative periods at the activity level. Time phasing is based
on the Earned Value (EV) method, defined for the activity.
Select the required activity and click Time Phased Hours by
Project/ Activity/ Cost Component or Time Phased Hours by Project/ Activity/
Control Code to view the report for:
The time phased budget data and the actual hours utilized for
the project in the current and the cumulative periods at the project/ activity/
cost component level
The time phased budget data and the actual hours utilized for
the project in the current and cumulative periods at the project/ activity/
control code level
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated
The report displays:
Activity (Description)
The activity linked to the project.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Planned Hours
The estimated number of hours required for the completion
of the project in the current/ cumulative period. Calculations are based on the
Earned Value (EV) method, defined on the activity.
Actual Hours
The actual hours used to complete the project in the
current/ cumulative period.
Balance Hours
The balance hours in the current/ cumulative period,
calculated using the formula:
(Planned Hours - Actual Hours)
Balance Hours %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100
Time Phased Hours by Project/ Activity/ Cost Component
Time Phased Hours by Project/ Activity/ Cost Component
The Time Phased Hours by Project/ Activity/ Cost Component
report displays the time phased budget data and the actual hours utilized for
the project in the current and the cumulative periods, at the cost component
level. Time phasing is based on the Earned Value (EV) method, specified for the
activity.
Note
At the cost component level and the control code level, the time
phased hours report is displayed only for the cost type; Labor.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Activity (Description)
The activity linked to the project.
The report displays:
Cost Component (Description)
The cost component linked to the project.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Planned Hours
The estimated number of hours required for the completion
of the project in the current/ cumulative period. Calculations are based on the
Earned Value (EV) method, defined on the activity.
Actual Hours
The actual hours used to complete the project in the
current/ cumulative period.
Balance Hours
The balance hours in the current/ cumulative period,
calculated using the formula:
(Planned Hours - Actual Hours)
Balance Hours %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours))/ Planned Hours))*100
Time Phased Hours by Project/ Activity/ Control Code
Time Phased Hours by Project/ Activity/ Control Code
The Time Phased Hours by Project/ Activity/ Control Code report
displays the time phased budget data and the actual hours utilized for the
project in the current and the cumulative periods, at the control code level.
Time phasing is based on the Earned Value (EV) method, specified for the
activity.
Note
At the cost component level and the control code level, the time
phased hours report is displayed only for the cost type; Labor.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated
Activity (Description)
The activity linked to the project.
The report displays:
Control Code (Description)
The control code linked to the project.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Planned Hours
The estimated number of hours required for the completion
of the project in the current/ cumulative period. Calculations are based on the
Earned Value (EV) method, defined on the activity.
Actual Hours
The actual hours used to complete the project in the
current/ cumulative period.
Balance Hours
The balance hours in the current/ cumulative period,
calculated using the formula:
(Planned Hours - Actual Hours)
Balance Hours %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100
Cost Forecast
Cost Forecast
Cost Forecast by Project
Cost Forecast by Project
The Cost Forecast report allows the project manager to analyze
the expected future costs, the total cost required to complete the project and
determine the budget variance.
Select the required project to view the forecast data of the
project at the activity level.
To generate the report, specify:
Currency Type
The type of the currency based on which the report is
generated.
Company
The code of the company.
Project
The project (range) for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
The section of economy related to business and corporate
organizations. Projects can be categorized based on the business
sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the projects.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
The report displays this data:
Budget
The budget data is based on the last approved version in the
BI.
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion
Cost Forecast by Project/ Activity
Cost Forecast by Project/ Activity
The Cost Forecast by Project/ Activity report allows the project
manager to analyze the expected future costs, the total cost required to
complete the project and determine the budget variance, at the activity
level.
Select the required activity to view the forecast data of the
project at the project/ activity/ control code level.
To generate the report, specify:
Company
The code of the company.
Project
The project (range) for which budget report is
generated.
Currency Type
The type of the currency based on which the report is
generated.
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion
Cost Forecast by Project/ Activity/ Control Code
Cost Forecast by Project/ Activity/ Control Code
The Cost Forecast by Project/ Activity/ Control Code report
allows the project manager to analyze the expected future costs, the total cost
required to complete the project and determine the budget variance, at the
control code level.
To generate the report, specify:
Company
The code of the company.
Project
The project (range) for which budget report is
generated.
Activity (Description)
The activity linked to the project.
Currency Type
The type of the currency used to display the data in the
report.
The report displays this data:
Control Code (Description)
The control code linked to the project.
Currency
The currency used to display the data in the report. Note: This value is based
on the selected Currency Type.
Budget
The budget data is based on the last approved version in the
BI.
Actual Cost
The cost data is populated from Infor LN.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Cost
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion
Hours Forecast by Project
Hours Forecast by Project
The Hours Forecast by Project report allows the project manager
to analyze the planned hours, the actual hours utilized to complete the project
and determine the variance, for the specified range of data.
Select the required project to view the hours forecast data of
the project at the activity level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
An area of commercial endeavor. Projects can be categorized
based on the business sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the project.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
The report displays:
Project
The project for which the forecast report is
generated.
Planned Hours
The budgeted number of hours required for the completion of the
project.
Actual Hours
The actual number of hours utilized to complete the
project.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Hours
Variance At Completion is the difference between the
budgeted hours and the estimated hours, at the completion of the
project.
Variance At Completion = Planned Hours - Estimate At Completion
Hours Forecast by Project/ Activity
Hours Forecast by Project/ Activity
The Hours Forecast by Project/ Activity report helps the project
manager to analyze the planned hours, the actual hours utilized to complete the
project and determine the variance; at the activity level.
Select the required activity to view the hours forecast data of
the project at the project/ activity/ control code level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Variance At Completion is the difference between the
budgeted hours and the estimated hours, at the completion of the
project.
Variance At Completion = Planned Hours - Estimate At Completion
Hours Forecast by Project/ Activity/ Control Code
Hours Forecast by Project/ Activity/ Control Code
The Hours Forecast by Project/ Activity/ Control Code report
allows the project manager to analyze the planned hours, the actual hours
utilized to complete the project and determine the variance; at the control
code level.
Note
The hours forecast report at the control code level is displayed
only for the cost type, Labor.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Activity (Description)
The activity linked to the project.
The report displays:
Control Code (Description)
The control code linked to the project.
Planned Hours
The estimated number of hours required for the completion of
the project.
Actual Hours
The actual number of hours utilized to complete the
project.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Hours
Variance At Completion is the difference between the
budgeted hours and the estimated hours, at the completion of the
project.
Variance At Completion = Planned Hours - Estimate At Completion
Earned Value Management
Earned Value Management
Project Performance
Project Performance
The Project Performance report allows you to review the
performance indices of the project. These are calculated using the earned value
and the variance data for the current and cumulative periods.
Select the required project and click Project Performance by
Project/ Activity or Project Performance by Project/ OBS to view the report
for:
The performance data of the project at the activity
level
The index is calculated by dividing earned value with planned
value.
EV Method in Infor LN
EV
calculation is based on
Percent Complete
Progress
defined in Infor LN for the activity
Start and End Percent
Start and end
date of the activity
Milestone
Milestone completion
date
Level of Effort
Effort to complete the
project
Apportioned
Distribution of the Earned
value
Project Performance by Project/ Activity
Project Performance by Project/ Activity
The Project Performance by Project/ Activity report displays the
performance indices. These are calculated using the earned value and variance
data of the project for the current and cumulative periods, at the activity
level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Currency Type
The type of the currency based on which the report is
generated.
Period (Monthly)
The period (range) of the year for which the report is
generated.
The Project Performance report displays this data:
Activity (Description)
The activity linked to the project.
Currency
The currency in which the report data is displayed. Note: This value is based
on the selected Currency Type.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Planned Value
The amount of work planned in the current/ cumulative
period.
Earned Value
The amount of work completed in the current/ cumulative
period.
Actuals
The actual cost incurred for the task in the current/
cumulative period.
Cost variance
The difference between the estimated cost and the actual
cost incurred for the task.
Cost variance = Earned value - Actuals
Schedule variance
The time period by which a project is ahead of or behind
the schedule.
The Project Performance by Project/ OBS report displays the
performance indices of the project. These are calculated using the earned value
and the variance data of the project for the current and cumulative periods, at
the organization breakdown structure (OBS) level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Currency Type
The type of the currency used to display the data in the
reports.
Period (Monthly)
The period (range) of the year for which the report is
generated.
The index is calculated by dividing the earned value with
planned value.
EV Method in Infor LN
EV
calculation is based on
Percent Complete
Progress
defined in Infor LN for the activity
Start and End Percent
Start and end
date of the activity
Milestone
Milestone completion
date
Level of Effort
Effort to complete the
project
Apportioned
Distribution of the Earned
value
Project Scheduling
Project Scheduling
The project schedule status allows the project manager to track
the project schedule and identify variances for the project, if any. The report
allows you to review the project performance with respect to the schedule
adherence.
To view the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.