The Project Performance report allows you to review the
performance indices of the project. These are calculated using the earned value
and the variance data for the current and cumulative periods.
Select the required project and click Project Performance by
Project/ Activity or Project Performance by Project/ OBS to view the report
for:
The performance data of the project at the activity
level
The index is calculated by dividing earned value with planned
value.
EV Method in Infor LN
EV
calculation is based on
Percent Complete
Progress
defined in Infor LN for the activity
Start and End Percent
Start and end
date of the activity
Milestone
Milestone completion
date
Level of Effort
Effort to complete the
project
Apportioned
Distribution of the Earned
value
Project Performance by Project/ Activity
Project Performance by Project/ Activity
The Project Performance by Project/ Activity report displays the
performance indices. These are calculated using the earned value and variance
data of the project for the current and cumulative periods, at the activity
level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Currency Type
The type of the currency based on which the report is
generated.
Period (Monthly)
The period (range) of the year for which the report is
generated.
The Project Performance report displays this data:
Activity (Description)
The activity linked to the project.
Currency
The currency in which the report data is displayed. Note: This value is based
on the selected Currency Type.
Period/ Cumulative
Year
The current/ cumulative year for which the report is
generated.
Period
The current/ cumulative period of the year for which the
report is generated.
Planned Value
The amount of work planned in the current/ cumulative
period.
Earned Value
The amount of work completed in the current/ cumulative
period.
Actuals
The actual cost incurred for the task in the current/
cumulative period.
Cost variance
The difference between the estimated cost and the actual
cost incurred for the task.
Cost variance = Earned value - Actuals
Schedule variance
The time period by which a project is ahead of or behind
the schedule.
The Project Performance by Project/ OBS report displays the
performance indices of the project. These are calculated using the earned value
and the variance data of the project for the current and cumulative periods, at
the organization breakdown structure (OBS) level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Currency Type
The type of the currency used to display the data in the
reports.
Period (Monthly)
The period (range) of the year for which the report is
generated.