The Cost Forecast report allows the project manager to analyze
the expected future costs, the total cost required to complete the project and
determine the budget variance.
Select the required project to view the forecast data of the
project at the activity level.
To generate the report, specify:
Currency Type
The type of the currency based on which the report is
generated.
Company
The code of the company.
Project
The project (range) for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
The section of economy related to business and corporate
organizations. Projects can be categorized based on the business
sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the projects.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
The report displays this data:
Budget
The budget data is based on the last approved version in the
BI.
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion
Cost Forecast by Project/ Activity
Cost Forecast by Project/ Activity
The Cost Forecast by Project/ Activity report allows the project
manager to analyze the expected future costs, the total cost required to
complete the project and determine the budget variance, at the activity
level.
Select the required activity to view the forecast data of the
project at the project/ activity/ control code level.
To generate the report, specify:
Company
The code of the company.
Project
The project (range) for which budget report is
generated.
Currency Type
The type of the currency based on which the report is
generated.
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion
Cost Forecast by Project/ Activity/ Control Code
Cost Forecast by Project/ Activity/ Control Code
The Cost Forecast by Project/ Activity/ Control Code report
allows the project manager to analyze the expected future costs, the total cost
required to complete the project and determine the budget variance, at the
control code level.
To generate the report, specify:
Company
The code of the company.
Project
The project (range) for which budget report is
generated.
Activity (Description)
The activity linked to the project.
Currency Type
The type of the currency used to display the data in the
report.
The report displays this data:
Control Code (Description)
The control code linked to the project.
Currency
The currency used to display the data in the report. Note: This value is based
on the selected Currency Type.
Budget
The budget data is based on the last approved version in the
BI.
Actual Cost
The cost data is populated from Infor LN.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Cost
Variance At Completion is the difference between the
budgeted amount and the estimated amount at the end of the project.
Variance At Completion = Budget - Estimate At Completion
Hours Forecast by Project
Hours Forecast by Project
The Hours Forecast by Project report allows the project manager
to analyze the planned hours, the actual hours utilized to complete the project
and determine the variance, for the specified range of data.
Select the required project to view the hours forecast data of
the project at the activity level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Status
The project status.
Acquiring Method
The method used to acquire the project.
Financing Method
The financing method used for the project.
Business Sector
An area of commercial endeavor. Projects can be categorized
based on the business sector.
Geographical Area
The geographical area associated with the project.
Category
The user-defined classification of the project.
Program
A group of related projects managed in a coordinated way to
obtain more benefits and control.
Project Manager
The employee who manages the project.
The report displays:
Project
The project for which the forecast report is
generated.
Planned Hours
The budgeted number of hours required for the completion of the
project.
Actual Hours
The actual number of hours utilized to complete the
project.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Hours
Variance At Completion is the difference between the
budgeted hours and the estimated hours, at the completion of the
project.
Variance At Completion = Planned Hours - Estimate At Completion
Hours Forecast by Project/ Activity
Hours Forecast by Project/ Activity
The Hours Forecast by Project/ Activity report helps the project
manager to analyze the planned hours, the actual hours utilized to complete the
project and determine the variance; at the activity level.
Select the required activity to view the hours forecast data of
the project at the project/ activity/ control code level.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Variance At Completion is the difference between the
budgeted hours and the estimated hours, at the completion of the
project.
Variance At Completion = Planned Hours - Estimate At Completion
Hours Forecast by Project/ Activity/ Control Code
Hours Forecast by Project/ Activity/ Control Code
The Hours Forecast by Project/ Activity/ Control Code report
allows the project manager to analyze the planned hours, the actual hours
utilized to complete the project and determine the variance; at the control
code level.
Note
The hours forecast report at the control code level is displayed
only for the cost type, Labor.
To generate the report, specify:
Company
The code of the company.
Project
The code of the project for which the report is
generated.
Activity (Description)
The activity linked to the project.
The report displays:
Control Code (Description)
The control code linked to the project.
Planned Hours
The estimated number of hours required for the completion of
the project.
Actual Hours
The actual number of hours utilized to complete the
project.
Forecast
Estimate To Complete (ETC)
Estimate To Complete is the additional cost incurred for
an activity or a project.
Estimate To Complete = Estimate At Completion - Actual Hours