Search criteria for costing breaks

Infor LN uses a search criteria for costing breaks defined for the production resources and production materials either for a specific project or a blank project.

The search criteria that Infor LN follows; for costing breaks:

  1. Costing breaks defined for the production resources for the specific project.
  2. Costing breaks set up for the production resources for a blank project.
  3. Costing breaks set up for the production material for the specific project.
  4. Costing breaks set up for the production material for a blank project.

The hierarchical search sequence applicable for production (material and resources):

Production typeIIIIIIIVV
Production -MaterialMain item / BOM Component itemItem group / Main itemonly the Main itemonly the BOM Component itemItem group
Production -ResourcesMain item / Routing / OperationsMain item / RoutingWork centerCost type / Main item

 

Note
  1. For production material; you can use the Import Item Groups and the Import Components options to set up costing break for multiple item groups and component items of the main item.
  2. For production resources; you can use the Import Operations and the Import Work Centers options to set up costing break for multiple routing operations and work centers.

The hierarchical search sequence applicable for service depot repair:

Service typeIIIIIIIVV
Service Depot Repair MaterialService item groupInstallation groupService item (Main Item)Serialized item (Item)Item serial number
Service Depot Repair LaborMaster routingRouting optionReference activityTask
Service Depot Repair OtherItem groupItemCost Type level for Tooling, Subcontracting and Other costs.

 

Note
  1. For service depot repair material; you can use the Import Service Item Groups and the Import Installation Groups options to set up costing break for multiple service item groups and installation groups.
  2. For service depot repair labor; you can use the Import Master Routings option to set up costing break for multiple master routings.
  3. For service depot repair other; you can use the Import Item Groups option to set up costing break for multiple item groups.