An activity budget line can have the following statuses:
Free A
budget line with this status is not included in control data. You can still
change the budget line.
Actual You can keep the history with this status. If the Actual check box in the Project Budget Parameters (tpptc0100s000) session is selected, you can generate control data for
these budget lines.
Final You cannot maintain a budget line that has this status. You cannot change the
activity anymore and you can only change its corresponding budget (activity or
time-phased) with an adjustment. If the Final check box in the Project Budget Parameters (tpptc0100s000) session is selected, You can generate control data.
Note
If you select a new
budget status for the activity, the status of the budget lines is also
modified.