To Maintain a Budget Cost Analysis

Step 1. 

Use the Budget Cost Analysis Version (tpptc3100s000) session to create a new budget cost analysis version for the selected project.

Step 2. 

Use the Generate Budget Cost Analysis (tpptc3200m000) session to generate the analysis data, and specify the budget cost analysis version against which you want that analysis data stored.

Step 3. 

Output your required budget information from the analysis data using any of the display or print sessions available from the Budgeted Project Costs (tpptc3801m000) session.