To generate planned valueUse the Generate Time-Phased Budget (tpptc5200m000) session to make the budget time-phased for a selected time-phased-budget-analysis code and top down budget version. The output of this session is the planned value. You can run the session for one or a range of projects. The following details default from the Time Phased Budget Analysis Codes by Project (tpptc5120s000) session, but you can override the data in the Generate Time-Phased Budget (tpptc5200m000) session:
The calculation of the planned value depends on the earned-value-method-related data of the activities, which are used as leaf nodes in the version. The planned value of those activities will be aggregated through the whole planned value. You can view the planned value with the Time Phased Budget (Planned Value by Period) (tpptc5521m000) session, and print a report with the Print Planned Value by Period (tpptc5421m000) session.
| |||