Publish Project Data (tpbod0200m000)

Use this session to publish LN Project data to Infor ION for transfer to other software applications.

The following Project data can be published:

  1. Projects
  2. Labor costs
  3. Sundry costs
  4. Project balances
  5. Project period balances
  6. Project costs
  7. Project extensions
  8. Project bids
  9. Project estimates
  10. Project installments (revenues)
  11. Project budgets
  12. Project progress

If errors occur during the publication process or if other software applications require a new set of data, you can run this session again.

Note
  • The tabs in this session represent the nouns in a Business Object Document (BOD).
  • Publishing is not target specific, which means that messages are delivered to all subscribers.

 

Options
Mode
Size

The number of records that must be simulated.

If you enter a value of 100, the first 100 records that fall within the selection criteria must be simulated.

Default value

The default value is zero, which means all records that fall within the selection range are simulated.

Note

This field is enabled only if the Mode field is set to Simulate

Selection Range
Company

The company range for which the data must be published.

Settings
Use Verb

Specify the type of BODs that must be published.

Allowed values

Use Verb

Note

This field is enabled only if the Mode field is set to Simulate.

Logical ID(s)

Show BODs do not use ION routes and are sent directly to other applications. Use this field to specify the logical ID(s) of the receiving application.

Note

This field is enabled only if the Use Verb field is set to Use Show Verb.

Logging
Logging

If this check box is selected, published BODs are logged.

Output

Specify the log output.

Allowed values

Subject BOD Logging

Note

This field is enabled only if the Logging check box is selected.

Single XML-file per BOD

If this check box is selected, a separate log file is generated for each published BOD.

If this check box is cleared, one log file is generated with the xml of all published BODs.

Note

This check box is only available if the Output field is set to BOD.

Location

The server or client to which the output files must be written.

Note

This field is enabled only if the Logging check box is selected.

Directory

The directory on the server or client to which the output files must be written.

Note

This field is enabled only if the Logging check box is selected.

ProjectMaster
ProjectMaster

If this check box is selected, projects with their activity structure are published.

ProjectExtension
ProjectExtension

If this check box is selected, extensions are published.

Related topics

LaborCostMaster
Standard

If this check box is selected, standard labor cost objects are published.

Project

If this check box is selected, project-specific labor cost objects are published.

SundryCostMaster
Standard

If this check box is selected, standard cost objects relating to sundry costs are published.

Project

If this check box is selected, project-specific cost objects relating to sundry costs are published.

ProjectBalance
ProjectBalance

If this check box is selected, cost control by activity is published.

ProjectPeriodBalance
ProjectPeriodBalance

If this check box is selected, performance measurement by activity/ cost type is published

Related topics

ProjectBid
ProjectBid

If this check box is selected, bids are published.

Related topics

ProjectCosts
History

If this check box is selected, the history data related to the project costs is published.

Interim Results

If this check box is selected, the interim results related the project costs are published.

EAC Material

If this check box is selected, the estimate at completion material data related to the project costs is published.

EAC Labor

If this check box is selected, the estimate at completion labor data related to the project costs is published.

EAC Equipment

If this check box is selected, the estimate at completion equipment data related to the project costs is published.

EAC Subcontracting

If this check box is selected, the estimate at completion subcontracting data related to the project costs is published.

EAC Sundry

If this check box is selected, the estimate at completion sundry costs related to the project costs are published.

EAC Overhead

If this check box is selected, the estimate at completion overhead related to the project costs are published.

ProjectEstimate
ProjectEstimate

If this check box is selected, estimates are published

Related topics

ProjectRevenue I
Manual

If this check box is selected, the manually specified project revenues are published.

History

If this check box is selected, the history data related project revenues is published.

Interim Results

If this check box is selected, the interim results related to the project revenues are published.

ProjectRevenue II
Advance Payment Request

If this check box is selected, the advance payment requests related to the project revenues are published.

Installment

If this check box is selected, the installments related to the project revenues are published.

Related topics

Installment Extra Work

If this check box is selected, the extra work of the installments related to the project revenues is published.

Holdback

If this check box is selected, the holdbacks related to the project revenues is published.

Fees

If this check box is selected, the contract fee related to the project revenues are published.

Progress Payment Request

If this check box is selected, the progress payment requests related to the project revenues are published.

Delivery Based

If this check box is selected, the delivery based invoices related to the project revenues are published.

ProjectBudget
ProjectBudget

If this check box is selected, project budgets are published.

Time Phased

If this check box is selected, Infor LN publishes project budgets in a time phased manner.

ProjectProgress
ProjectProgress

If this check box is selected, project activity progress is published.

Progress is retrieved from the Activity Physical Progress (tpppc1560m000) session.

ProjectContract
ProjectContract

If this check box is selected, the contracts linked to the projects are published.

The contracts are retrieved from the Contracts (tpctm1100m000) session.

ProjectContractDeliverable
Label is set in script

If this check box is selected, the contract deliverables related to the project are published.

ProjectContractInstallment
Label is set in script

If this check box is selected, the contract installments related to the project are published.

Specific
LnUserDefinedStructure

If this check box is selected, the user defined structure related to the project is published.

Label is set in script

If this check box is selected, the billing cycle of the contract related to the project is published.

 

Process

Publishes the data to Infor ION.