Select how the production orders are chosen.
Allowed values
- By Order
- By Group
Shift Production Planning (tisfc1202m000)Use this session to shift the production planning. If you create a delay by postponing the production planning, you can use the delay, for example, to cope with a backlog in production.
Selection Select how the production orders are chosen. Allowed values
Site A business location of an enterprise that can maintain its own logistical data. It includes a collection of warehouses, departments and assembly lines at the same location. Sites are used to model the supply chain in a multisite environment. These restrictions apply to sites:
You can link a site to an enterprise unit or an enterprise unit to a site. If an enterprise unit is linked to a site, the entities of the site belong to the enterprise unit. Conversely, if a site is linked to an enterprise unit, the entities of the enterprise unit belong to the site. Order Enter the range of production orders whose operations you want to delay. Planner The logon code of the employee who plans plan items. Shop Floor Planner The person responsible for printing, (re)scheduling and releasing production orders and managing workloads. Routing Group A group of items with similar routing attributes, for example, the same work center, routing operation, BOM, and so on. A routing group is defined by the user as a selection criterion for production orders. Product Line A group of products made by the same producer, that are similar but differ in details such as, size, shape, color, and so on. User-definable item grouping data, mainly used as an item selection criterion for reporting. Product Class User-definable item grouping data that is used to distinguish between different groups of items in a product line. The product class is mainly used as a selection criterion for reporting. Selection Code User-definable item grouping data. Use selection codes to select items by color, diameter, product expiry date, and so on. Note Selection codes are used for information purposes only. Production Order Group Enter the JSC order group whose production orders you want to shift. Current Date The system date. Direction The planning method that determines in which direction the production planning dates are shifted. Allowed values
Shift Planning to Date The date to which you want to shift your production planning. How the production planning is exactly shifted depends on whether you already worked on the production order:
Simulation If this check box is selected, a report is generated listing the production orders that can be replanned, and the reasons if orders cannot be shifted. Message When Order is Late If this check box is selected, LN will inform you when an order is not Completed, and it is past its latest finish date.
Shift Click to carry out the process that you set up in this session.
| |||