| Shared Work Center Relationships (tirou3100m000)You must already have
defined the work centers as a shared work center in the Work Centers (tirou0101m000) session. When you create the
relationship, the data about the primary work center is copied to the secondary
work center. As a result, you can no longer edit the secondary work center data
in the Work Centers (tirou0101m000) session, except for its description, the shop floor
warehouse and backflush employee. Note The total percentage
of the capacity primary work center that is allocated to various secondary work
centers can be more than 100%, to allow for overtime and other factors. As a
rule, you must usually make sure that this value is less than or equal to 100%. Shared Primary Work Center A work center that does not have any physical resources and
cannot be modeled in a routing. It is used for capacity planning and displays
the total capacity requirements of the shared work centers. The work is
actually carried out in shared secondary work centers, which can be in the same
or a different logistical company than the primary work center. This enables
you to plan and carry out work in several different logistical companies (if
you define several secondary work centers) without having to use sales orders
and purchase order. Note You must already
have defined a primary work center in the Work Centers (tirou0101m000) session. Shared Work Center Company The secondary work center company. In this session, you can assign a part of the capacity of a primary
work center to several different seconday work centers, each in a different
company. The following restrictions apply: - The company must be
present in your package combination (refer to the Packages by Package Combination (ttaad1121m000) session).
- The company must be
different from the primary work center's company.
- You cannot use
company 000.
- You must be
authorized for the company.
- The primary work
center must not already be related to a secondary work center of this company.
Shared Secondary Work Center The secondary work center. In
this session, you can assign a part of the capacity of a primary work center to
several different seconday work centers, each in a different company. Note The secondary work
center must already be defined as a secondary work center in the Work Centers (tirou0101m000) session and it cannot already be assigned to another
primary work center. Date Established LN enters today's date by default. Percentage Capacity In this session, you can assign a part of the capacity of a primary work center to
several different secondary work centers, each
in a different company. This field shows
what percentage is assigned to the secondary work center. Note The total percentage
of the primary work center that is allocated to various secondary work centers
can be more than 100%, to allow for overtime and other factors. As a rule, you
must make sure that this value is 100% or less. | |