| Aggregate Estimated Capacity to Project (tipcs4201m000)Use this session to aggregate each project's capacity requirements on the
basis of detailed project engineering of the project in order to determine the
aggregated capacity-requirements by activity. Project A collection of manufacturing and purchasing actions that are
performed for a particular customer order. A project is initiated to plan and
coordinate the production of the to be manufactured items. For a standard-to-order production, the project is only
used to link the item with the customer order. A project can also include
these: - Customized item data (BOMs and routings)
- Project planning (activity planning)
Link Operations to Activities If this check box is selected, the customized
operations are automatically linked to an activity in the activity
network. This goes as follows: - If the activity code
in the Activities (tipcs4101m000) session has not been filled in, or if you indicated
that the code can be overwritten, LN first searches for an activity in which the
task AND the work center of the activity match the task and the work center of
the customized operation.
- If this activity
code is not present, LN searches for an activity in which the task OR the work center of the activity
matches with the task or work center of the customized operation.
- If this activity
code is not present, LN searches for an activity in which the main work center of the activity matches
the main work center of the customized operation.
- LN, finally, reports if the
customized operation cannot be linked to an activity.
Overwrite Activity Code If this check box is selected, the customized
operations which have already been linked to an activity are re-linked to an
activity in the activity network. | |