Production SchedulingThe objective of the Production Scheduler (tirpt4202m200) session is to create feasible schedules for the work cells that are linked to the same plan group. First the scheduler schedules finite forward. The result is a feasible plan that doesn’t start in the past, doesn’t have overlap, but some supplies can be late. By swapping runs to reduce cumulative lateness, swapping lines in a work cell to reduce lateness and offloading runs if a run to produce the items in another work cell you can streamline the scheduling.
| |||