Module Planning - OverviewProject Control relies on components with long lead-times being available on time. When the sales order demand is not yet entered, or when the bill of material (BOM) for the customized product structure is not ready, Enterprise Planning cannot properly plan these critical materials. To compensate for this, a fixed planning quantity for the components can be specified in the Module Planning (tipcs4120m000) session. When generating an order planning, Enterprise Planning will create planned supply for these components. When the actual sales order is entered or engineering on the BOM is completed and there is still a fixed plan quantity on the module, the generated order planning orders too much supply. A signal is raised for the user to clear the Fixed Plan Quantity check box on the module so the module planning is no longer taken in to account. The module demand is handled differently from regular demand, like sales order demand.
Note
When multiple module demands exist for the same planned item, supply for all demands is combined in to one firm planned supply order, unless order intervals are defined in the item ordering data. When both module demand and regular demand exist for an item, Generate Order Planning (cprrp1210m000) performs these steps:
Note
Example The Item Order Plan (cprrp0520m000) shows that an item has a module demand for 4 pieces of material on 24 December 2013, and a sales order of 6 pieces on 25 February 2013. This results first in a firm planned production order on 24 December 2013 for the module demand. It also fulfills part of the sales order, creating the exception message ("Demand will be delivered late."). For the remaining 2 pieces of the sales order, a planned distribution order is created to consume the on-hand inventory of the derived-from item.
| |||