| Rescheduling Production OrdersTo reschedule a range of JSC production orders in the Reschedule Production Orders (tisfc3240m000) session by order or order group: Select By Group in the selection range. Select to which site the selection applies, if multisite functionality is activated. Select a range of JSC Order Groups in the Group Selection group box. - Select the desired print options in the Processing Print Options group box.
- Click Continue. The Reschedule Production Orders (tisfc3140m000) session starts. This session displays a list of
all JSC production orders falling within the selection range.
- Per production order, change the Modified Production Start Date and the Modified Requested Delivery Date.
- On the appropriate menu, click Process Production Orders.
- If you selected one or more print options, the Select Device (ttstpsplopen ) session starts. Specify an output device for printing
the reports.
- Click Continue. The selected orders are rescheduled and a
report is printed.
| |