| Maintaining EBOM Copy DataYou can use the following sessions and menu options to maintain
and manage EBOM copy data. Data selection To create the copy data for a single-level of a BOM, select
a parent E-item of a particular revision from which the
data originates, and a parent item to which the data is to
be copied. The parent item is the item at the next higher level in the BOM
structure compared to the component(s) for which you record the copy data. If a relationship does not already exist between the
E-items and items, LN generates the link when you save the data. To copy the data You can copy the data you generate in this session with the Finalize Engineering Data (tiedm3240m000) session. If you want to copy only the
data that you see in the current view, you can select the Copy engineering data
option on the appropriate menu (CTRL+SHIFT+X).
| |