Recalculation of cycle time when changing man occupation or machine occupationIf you want to change the number of resources on an operation, you can do this by changing the value of the Man Occupation for Production field, or the Machine Occupation field in the Routing Operations (tirou1102m000) session, or the Production Planning (tisfc0110m000) session. If you want to avoid that the changed man occupation or machine occupation results in changed production costs, you must click Yes if LN asks the question whether to recalculate the cycle time. If you do so, LN calculates the following: Changed machine occupation New Cycle Time = (Old machine occupation / New machine occupation) * Old Cycle Time New Man Occupation = (Old Man Occupation * Old Cycle Time) / New Cycle Time Example
Change machine occupation from 2 to 3. Result of recalculation
Automatically updated
Changed man occupation New Cycle Time = (Old man occupation / New man occupation) * Old Cycle Time New Machine Occupation = (Old Machine Occupation * Old Cycle Time) / New Cycle Time Example
Change man occupation from 1 to 2. Result of recalculation
Automatically updated
| |||||||||||||||||||||||||||||||