Actual costing and backflushingIf you use actual costing, the backflushing of material and/or hours can be a factor of complication. All backflushing must be performed before an end-item is received in the end-item warehouse. If backflushing is not performed before the end-item is received in the warehouse, the costs are not included in the end-item's standard cost. Consequently, the costs are not included in inventory valuation. Actual costing and backflushing for production orders with
operations If you use actual costing in combination with backflushing, it is important that the backflushing is done before the end item is received in the specified warehouse. If the Backflushing Method is set to Manual in the Production Order Parameters (tisfc0100s000) session the procedure is:
If the Backflushing Method field in the Production Order Parameters (tisfc0100s000) is set to Interactive, then the same result can be achieved by answering Yes to the question "Backflush materials/hours immediately?" If the Backflushing Method field in the Production Order Parameters (tisfc0100s000) is set to Automatic, the end item can be posted to inventory. Actual costing and backflushing for production orders without
operations If you use actual costing and backflushing, and you have NO operations defined for your production order, LN also uses a built-in check to minimize the risk of booking costs too late. The procedure is as follows:
| |||