| Operation StatusPlanned The status when the plan is created. Ready to Start When there is enough Quantity Completed on all the previous operations to report complete the minimum order quantity of
the operation in the Report Operations Completed (tisfc0130m000) session, the
operation status is set to Ready to Start by the previous operation. Started If you use LN the operation status is Started when any quantity is reported as completed in Job Shop Control. Active A WIP transaction has been performed on this operation. When the first
operation is set to Active,
the order status becomes Active too. Blocked The operation has been blocked in Job Shop Control by the
user or by an inspection order. Refer to Blocking operations. Completed All the work has been completed for the operation. The
quantities reported as completed and rejected are final. You can set this
status in the Report Operations Completed (tisfc0130m000) details
session. If required, you can click Reset Operation Status in the Report Operations Completed (tisfc0130m000) details session to change the operation
status from Completed back to Active. Closed The financial results of the operation have been calculated.
Operations can only be closed in LN.
| |