| Production Run Schedule StatusFree Run schedule is controlled by the planning engine. Released Run schedule complete, changes can only be made
manually. Active Production run schedule is being implemented. Production Completed All schedule lines for the production run were completed, but
the run has not been closed. Completed All schedule lines for the production run were completed, and
all completed products were delivered into inventory. You can still account
hours and issue materials for the run schedule. Closed The run schedule was completed, changes can no longer be
made.
| |