Display Work-in-Process (ticst0550m000)

Use this session to display the work in process (WIP) for production orders.

 

Site

The site ID.

Note

Only visible if multisite functionality is active.

Related topics

Selection Range
Production Order

An order to produce a specified quantity of an item on a specified delivery date.

Order Status

The status assigned to a production order, which indicates the process stage of a production order. For example, Created, Printed, or Released.

Allowed values

Order Status

PCS Project

A collection of manufacturing and purchasing actions that are performed for a particular customer order. A project is initiated to plan and coordinate the production of the to be manufactured items.

For a standard-to-order production, the project is only used to link the item with the customer order. A project can also include these:

  • Customized item data (BOMs and routings)
  • Project planning (activity planning)
Costing Work Center

A work center, linked to a work center, that is used to calculate the end item unit costs, WIP transfers, and production results used to hold the financial transactions related to production orders.

The link between a costing work center, and a work center enables you to replan production order operations again. If required, you can change the work center that is used to carry out an operation without modifying the costing process.

Calculation Office

A work center of the type Costing that is used to determine the enterprise unit for a project, or production order and also has an administrative function.

Note

When linked to production orders, the Use as Calculation Office check box in the Work Centers (tirou0101m000) session must be selected for the work center.

Shop Floor Planner

The person responsible for printing, (re)scheduling and releasing production orders and managing workloads.

Aggregation Level
Aggregation Level

The level to which the WIP data is aggregated.

Allowed values

  • By Production Order
  • By Amount Type
  • By Cost Component
Project Peg

If this check box is selected, WIP transactions will be aggregated by project peg.

Settings
WIP Analysis Date

The date and time for which the sessions display the status of the WIP. The session includes all WIP transactions that are posted until this date.

Note

The default value is the current time and date.

Currency for details

The selection method for the currency in which the amounts are expressed.

You can select the following values:

  • Reference
    The session displays all amounts in the reference currency.
  • Calculation Office
    The session displays the details in the currency of the calculation office. The totals are displayed in the currency that you define in the Currency for totals field.
  • Department or Warehouse
    The session displays the details in the currency of the department related to the work center. The totals are displayed in the currency that you define in the Currency for totals field.
  • Currency Total
    The session displays all amounts in the currency that you define in the Currency for totals field.

Related topics

Currency for totals

The currency in which the totals are expressed.

Related topics

Exchange Rate Type

A way to group currency exchange rates. You can assign different currency exchange rates to different invoice-to business partners and/or to different types of transactions (purchase, sales, and so on).

You can modify this field only if the Currency System field in the Companies (tcemm1170m000) session is Standard for the current company.

Options
Exclude Already Printed Orders

If this check box is selected, LN skips the production orders for which the Reports Printed check box in the Production Order (tisfc0101s000) session has been cleared.

The Work in Process check box is displayed in the Production Order (tisfc0101s000) details session. To start the Production Order (tisfc0101s000) details session, in the Production Orders (tisfc0501m000) session select a production order and then, in the appropriate menu, click Production Order Details.

Suppress Zero WIP Values

If this check box is selected, the session does not display lines on which the IncomingWIP Value, Booked Results, OutgoingWIP Value, and WIP Amount fields all have the value zero or a value that is closer to zero than the value of the Tolerance field.

Tolerance

The tolerance for deciding if a WIP amount is considered equal to zero and not displayed in the session. For more information, refer to the Help of the Suppress Zero WIP Values check box.

Exclude Production Order/Completion

If this check box is selected, the session does not display the Production Order/Completion integration transaction.

LN creates the Production Order/Completion integration transaction if you report a production order complete. This transaction is posted to debit and credit on the same ledger account and does not change the WIP.

Include Subassemblies in Inventory

If this check box is selected, LN includes the value of the subassemblies that you already received in inventory in the WIP.

Company Owned Value

If this check box is selected, materials owned by you are included in the report.

Customer Owned Value

If this check box is selected, materials owned by the customer are included in the report.