Schedule Release Detail

  • Material Release

    Only material release transactions are sent. Shipping is carried out based on the Firm or Immediate requirement types, as shown in EDI message BEM MRL001, if you use BEMIS standards.

  • Shipping Schedule

    Both a material release and a shipping schedule are sent. Shipping is carried out based on the BEM SHP001 message.

  • Sequence Shipping Schedule

    A material release and a sequence shipping schedule are sent. Shipping is carried out based on the BEM SEQ001 message. This value can only be selected for pull schedules.

  • Shipping Schedule Only

    Only a shipping schedule is sent. No planning data is sent to the supplier.

  • Sequence Shipping Schedule Only

    Only a sequence shipping schedule is sent. No planning data is sent to the supplier. This value can only be selected for pull schedules.