| Possible valuesThe planning method can apply to either projects or production
orders. Forward For a production order, the planning of the production order is
based on a fixed start date. A delivery date is calculated from the order run
time. For a project, the network planning for the project is executed
on the basis of a fixed start date. When you start the planning in the Generate Network Planning (tppss2240m000) session, LN determines the
project's delivery date with a Forward planning method. Backward For a production order, the planning of the production order is
based on a fixed delivery date. A start date is calculated from the order run
time. For a project, the network planning for the project is executed
on the basis of a fixed delivery date. When you start the planning in the Generate Network Planning (tppss2240m000), LN determines the project's start date with a Backward planning method.
| |