| Create Order Group for Planned Orders (cppat3250m000) Actual Scenario The scenario that contains the operational master plan or order
plan, as opposed to scenarios used only for simulation, that is, what-if
analysis. The actual scenario is the only scenario from which you can
transfer planned orders to the execution level. Note You can only create
planned-order groups in the actual scenario. Automatic Update If this check box is selected, you can update the order group to include the
planned orders that currently match the order group criteria. Order Status The range of order statuses that LN must use to select
planned production orders. Start Date The range of start dates you want to use as a selection
criterion. Finish Date The range of finish dates that you want to use as a selection
criterion. Warehouse The range of warehouses that LN must use as a criterion to select planned
production orders for the order group. This criterion applies to the value of
the Destination Warehouse field in the Planned Orders (cprrp1100m000) session. Task (Current) Specify the first of a range of tasks that LN must use as a
criterion to select planned production orders for the order group. For every order, LN checks whether the
corresponding operations consist of tasks that are included in the task
selection range you must specify here. If this is not the case, LN does not include the
order in the order group. Task (Current) Specify the last of a range of tasks that LN must use as a
criterion to select planned production orders for the order group. For every order, LN checks whether the
corresponding operations consist of tasks that are included in the task
selection range you must specify here. If this is not the case, LN does not include the
order in the order group. Work Center (Current) Specify the first of a range of work centers that LN must use to select
planned production order for the order group. For every order, LN checks whether the
work center linked to each operation carried out to produce the concerned item,
is included in the work center range you must specify here. If this is not the
case, LN does not include
the order in the order group. Work Center (Current) Specify the last of a range of work centers that LN must use to select
planned production order for the order group. For every order, LN checks whether the
work center linked to each operation carried out to produce the concerned item,
is included in the work center range you must specify here. If this is not the
case, LN does not include
the order in the order group. Machine Specify the first of a range of machines that LN must use as a
criterion to select planned production orders for an order group. For every order, LN checks whether the
machines linked to each operation carried out to produce the concerned item,
are included in the machine selection range you must specify here. If this is
not the case, LN does not
include the order in the order group. Machine Specify the last of a range of machines that LN must use to select
planned production orders for an order group. For every order, LN checks whether the
machines linked to each operation carried out to produce the concerned item,
are included in the machine selection range you must specify here. If this is
not the case, LN does not
include the order in the order group. Routing Group Specify the first of a range of routing groups that LN must use as a
criterion to select planned production orders for an order group. Main Item If this check box is selected, you can use a range of
end items as a selection criterion for the order group. From Main Item Specify the first of a range of main items of which LN must combine the
planned production orders in an order group. To Main Item Specify the last of a range of main items of which LN must combine the
planned production orders in an order group. Material Item Selection If this check box is selected, you can use a range of
component items as a selection criterion for the order group. From Material Item Specify the first of a range of material items of which LN must combine the
planned production order in an order group. To Material Item Specify the last of a range of material items of which LN must combine the
planned production order in an order group. Item Group Specify the first of a range of item groups that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Item Group Specify the last of a range of item groups that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Planner Specify the first of a range of planners that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Planner Specify the last of a range of planners that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Shop Floor Planner Specify the first of a range of shop floor planners that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Shop Floor Planner Specify the last of a range of shop floor planners that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Product Line Specify the first of a range of product lines that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Production Line Specify the last of a range of product lines that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Product Class Specify the first of a range of product classes that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Product Class Specify the last of a range of product classes that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Selection Code Specify the first of a range of selection codes that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Selection Code Specify the last of a range of selection codes that LN must use as an
additional criterion to select planned production orders of main items for an
order group. Tool Kit Specify the first of a range of tool kits that LN must use as a
criterion to select planned production orders for an order group. Tool Kit Specify the last of a range of tool kits that LN must use as a
criterion to select planned production orders for an order group. From Tool Type Specify the first of a range of tool types that LN must use as a
criterion to select planned production orders for the new order
group. To Tool Type Specify the last of a range of tool types that LN must use as a
criterion to select planned production orders for the new order
group. Tool Serial Number Specify the first of a range of tool serial numbers that LN must use as a
criterion for the tool type selection range. Tool Serial Number Specify the last of a range of tool serial numbers that LN must use as a
criterion for the tool type selection range. Maximum Group Size The maximum number of orders that LN can add to the
planned-order group. Include Grouped Orders This check box determines how LN treats orders that
match the selection criteria, but which are already part of an existing order
group. If this check box is selected, and you click Create Group, the Assign Production Orders to Planned Order Group (cppat3151s000) session also displays the
planned production orders that belong to another order group. However, you
cannot select those planned orders for the new order group. If this check box is cleared, the Assign Production Orders to Planned Order Group (cppat3151s000) session hides these planned
orders. Group Description Enter a description for the planned-order group. | |